Game-theoretic modeling of curtailment rules and network investments with distributed generation

被引:40
作者
Andoni, Merlinda [1 ]
Robu, Valentin [1 ]
Fruh, Wolf-Gerrit [2 ]
Flynn, David [1 ]
机构
[1] Heriot Watt Univ, Inst Sensors Signals & Syst, Edinburgh, Midlothian, Scotland
[2] Heriot Watt Univ, Mech Proc & Energy Engn, Edinburgh, Midlothian, Scotland
基金
英国工程与自然科学研究理事会;
关键词
Curtailment; Network upgrade; Principles of Access; Wind energy; Leader-follower (Stackelberg) game; TRANSMISSION EXPANSION; DISTRIBUTION-SYSTEM; WIND-SPEED; PLANNING FRAMEWORK; ENERGY RESOURCE; POWER; MANAGEMENT; OPTIMIZATION; SIMULATION; SCHEMES;
D O I
10.1016/j.apenergy.2017.05.035
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Renewable energy has achieved high penetration rates in many areas, leading to curtailment, especially if existing network infrastructure is insufficient and energy generated cannot be exported. In this context, Distribution Network Operators (DNOs) face a significant knowledge gap about how to implement curtailment rules that achieve desired operational objectives, but at the same time minimise disruption and economic losses for renewable generators. In this work, we study the properties of several curtailment rules widely used in UK renewable energy projects, and their effect on the viability of renewable generation investment. Moreover, we propose a new curtailment rule which guarantees fair allocation of curtailment amongst all generators with minimal disruption. Another key knowledge gap faced by DNOs is how to incentivise private network upgrades, especially in settings where several generators can use the same line against the payment of a transmission fee. In this work, we provide a solution to this problem by using tools from algorithmic game theory. Specifically, this setting can be modelled as a Stackelberg game between the private transmission line investor and local renewable generators, who are required to pay a transmission fee to access the line. We provide a method for computing the equilibrium of this game, using a model that captures the stochastic nature of renewable energy generation and demand. Finally, we use the practical setting of a grid reinforcement project from the UK and a large dataset of wind speed measurements and demand to validate our model. We show that charging a transmission fee as a proportion of the feed-in tariff price between 15% and 75% would allow both investors to implement their projects and achieve desirable distribution of the profit. Overall, our results show how using game-theoretic tools can help network operators to bridge the knowledge gap about setting the optimal curtailment rule and determining transmission charges for private network infrastructure. (C) 2017 Published by Elsevier Ltd.
引用
收藏
页码:174 / 187
页数:14
相关论文
共 77 条
[1]   A multi-stage stochastic transmission expansion planning method [J].
Akbari, Tohid ;
Rahimikian, Ashkan ;
Kazemi, Ahad .
ENERGY CONVERSION AND MANAGEMENT, 2011, 52 (8-9) :2844-2853
[2]   Options for allocating and releasing distribution system capacity: Deciding between interruptible connections and firm DG connections [J].
Anaya, Karim L. ;
Pollitt, Michael G. .
APPLIED ENERGY, 2015, 144 :96-105
[3]   Experience with smarter commercial arrangements for distributed wind generation [J].
Anaya, Karim L. ;
Pollitt, Michael G. .
ENERGY POLICY, 2014, 71 :52-62
[4]  
Andoni M, 2016, IEEE PES INNOV SMART
[5]   Using Stackelberg Games to Model Electric Power Grid Investments in Renewable Energy Settings [J].
Andoni, Merlinda ;
Robu, Valentin .
AUTONOMOUS AGENTS AND MULTIAGENT SYSTEMS, 2016, 10002 :127-146
[6]  
[Anonymous], 2016, TECH REP
[7]  
[Anonymous], 2010, Market structure and equilibrium
[8]  
[Anonymous], 2011, INT C AUCT MARK MECH
[9]  
[Anonymous], 2015, LOW CARB NETW FUND
[10]  
[Anonymous], TECH REP