Challenges in line-of-balance scheduling

被引:90
作者
Arditi, D [1 ]
Tokdemir, OB
Suh, K
机构
[1] IIT, Dept Civil & Architectural Engn, Chicago, IL 60616 USA
[2] McDonagy Associates, Chicago, IL 60601 USA
[3] Honam Univ, Dept Civil Engn, Honam, South Korea
来源
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE | 2002年 / 128卷 / 06期
关键词
scheduling; construction management;
D O I
10.1061/(ASCE)0733-9364(2002)128:6(545)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The line-of-balance (LOB) method of scheduling is well suited to projects that are composed of activities of a linear and repetitive nature. The objective of this study is to set down the basic principles that can be used in the development of a computerized LOB scheduling system that overcomes the problems associated with existing systems and creates solutions to problems encountered in the implementation of repetitive-unit construction. The challenges associated with LOB scheduling include developing an algorithm that handles project acceleration efficiently and accurately, recognizing time and space dependencies, calculating LOB quantities, dealing with resource and milestone constraints, incorporating the occasional nonlinear and discrete activities, defining a radically new concept of criticalness, including the effect of the learning curve, developing an optimal strategy to reduce project duration by increasing the rate of production of selected activities, performing cost optimization, and improving the visual presentation of LOB diagrams.
引用
收藏
页码:545 / 556
页数:12
相关论文
共 18 条
  • [1] Arditi D., 1987, P NORDNET INTERNET P
  • [2] ARDITI D, 1999, INT J PROJ MANAGE, V15, P265
  • [3] ARDITI D, 1986, ASCE J CONSTRUCTION, V112, P411
  • [4] ASHLEY DB, 1980, J CONSTRUCT DIV-ASCE, V106, P185
  • [5] BORCHERDING JD, 1989, FACTORS HAVE ADVERSE
  • [6] *BUS ROUNDT, 1980, CONSTR IND COST EFF
  • [7] Linear scheduling model: Development of controlling activity path
    Harmelink, DJ
    Rowings, JE
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (04): : 263 - 268
  • [8] Scheduling projects with repeating activities
    Harris, RB
    Ioannou, PG
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (04): : 269 - 278
  • [9] Hegazy T., 1993, AACE T, VC.8, P81
  • [10] LUMSDEN P, 1968, LINE OF BALANCE METH