Linear programming based approaches for the discrete time/cost trade-off problem in project networks

被引:18
|
作者
Hafizoglu, A. B. [2 ]
Azizoglu, M. [1 ]
机构
[1] Middle E Tech Univ, Dept Ind Engn, TR-06531 Ankara, Turkey
[2] Arizona State Univ, Tempe, AZ 85287 USA
关键词
project management; Time/Cost Trade-off; Linear Programming; Branch and Bound;
D O I
10.1057/jors.2009.20
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In project management, the activity durations can often be reduced by dedicating additional resources. The Time/Cost Trade-off Problem considers the compromise between the total cost and the project duration. The discrete version of the problem assumes a number of time/cost pairs, called modes, and selects a mode for each activity. In this paper, we consider the Discrete Time/Cost Trade-off Problem. We study the Deadline Problem, that is, the problem of minimizing total cost subject to a deadline on the project duration. To solve the Deadline Problem, we propose optimization and approximation algorithms that are based on the optimal Linear Programming Relaxation solutions. Our computational results from large-sized problem instances reveal the satisfactory behaviour of our algorithms. Journal of the Operational Research Society (2010) 61, 676-685. doi: 10.1057/jors.2009.20 Published online 25 March 2009
引用
收藏
页码:676 / 685
页数:10
相关论文
共 50 条
  • [1] Optimal procedures for the discrete time cost trade-off problem in project networks
    Demeulemeester, EL
    Herroelen, WS
    Elmaghraby, SE
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 88 (01) : 50 - 68
  • [2] New computational results on the discrete time/cost trade-off problem in project networks
    Demeulemeester, E
    De Reyck, B
    Foubert, B
    Herroelen, W
    Vanhoucke, M
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1998, 49 (11) : 1153 - 1163
  • [3] On the discrete time, cost and quality trade-off problem
    Tareghian, Hamed R.
    Taheri, Seyyed Hassan
    APPLIED MATHEMATICS AND COMPUTATION, 2006, 181 (02) : 1305 - 1312
  • [4] Local search methods for the discrete time/resource trade-off problem in project networks
    De Reyck, B
    Demeulemeester, E
    Herroelen, W
    NAVAL RESEARCH LOGISTICS, 1998, 45 (06) : 553 - 578
  • [5] A Multi-objective Stochastic Programming Approach for Project Time, Cost and Quality Trade-off Problem (TCQTP)
    Ahadian, Behrooz
    Veisy, Omid
    Azizi, Vahid
    JORDAN JOURNAL OF CIVIL ENGINEERING, 2016, 10 (04) : 553 - 563
  • [6] Time-cost trade-off analysis of project networks in fuzzy environments
    Chen, Shih-Pin
    Tsai, Ming-Jiun
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 212 (02) : 386 - 397
  • [7] The discrete time/cost trade-off problem: extensions and heuristic procedures
    Mario Vanhoucke
    Dieter Debels
    Journal of Scheduling, 2007, 10 : 311 - 326
  • [8] Branch and bound based solution algorithms for the budget constrained discrete time/cost trade-off problem
    Degirmenci, G.
    Azizoglu, M.
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2013, 64 (10) : 1474 - 1484
  • [9] An Integer Grey Goal Programming For Project Time, Cost and Quality Trade-Off
    Hajiagha, Seyed Hossein Razavi
    Akrami, Hadi
    Hashemi, Shide Sadat
    Mahdiraji, Hannan Amoozad
    INZINERINE EKONOMIKA-ENGINEERING ECONOMICS, 2015, 26 (01): : 93 - 100
  • [10] Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows
    Ammar, Mohammad A.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (01): : 65 - 71