Maximizing the net present value of a project under uncertainty

被引:60
作者
Wiesemann, Wolfram [1 ]
Kuhn, Daniel [1 ]
Rustem, Berc [1 ]
机构
[1] Univ London Imperial Coll Sci Technol & Med, Dept Comp, London SW7 2AZ, England
基金
英国工程与自然科学研究理事会;
关键词
Project scheduling; Net present value; Optimization under uncertainty; STOCHASTIC PROGRAMS; SCHEDULING PROBLEM; CASH FLOWS; NETWORKS; MANAGEMENT; MODELS; RISK;
D O I
10.1016/j.ejor.2009.05.045
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
We address the maximization of a project's expected net present value when the activity durations and cash flows are described by a discrete set of alternative scenarios with associated occurrence probabilities. In this setting, the choice of scenario-independent activity start times frequently leads to infeasible schedules or severe losses in revenues. We suggest to determine an optimal target processing time policy for the project activities instead. Such a policy prescribes an activity to be started as early as possible in the realized scenario, but never before its (scenario-independent) target processing time. We formulate the resulting model as a global optimization problem and present a branch-and-bound algorithm for its solution. Extensive numerical results illustrate the suitability of the proposed policy class and the run-time behavior of the algorithm. (C) 2009 Elsevier B.V. All rights reserved.
引用
收藏
页码:356 / 367
页数:12
相关论文
共 42 条
[1]  
[Anonymous], 1970, Utility Theory for Decision Making
[3]   Resource-constrained project scheduling: Notation, classification, models, and methods [J].
Brucker, P ;
Drexl, A ;
Mohring, R ;
Neumann, K ;
Pesch, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :3-41
[4]   Activity delay in stochastic project networks [J].
Buss, AH ;
Rosenblatt, MJ .
OPERATIONS RESEARCH, 1997, 45 (01) :126-139
[5]  
BUSS AH, 1995, P 1995 WINT SIM C, P336
[6]   A robust optmization perspective on stochastic programming [J].
Chen, Xin ;
Sim, Melvyn ;
Sun, Peng .
OPERATIONS RESEARCH, 2007, 55 (06) :1058-1071
[7]   The stochastic time-cost tradeoff problem: A robust optimization approach [J].
Cohen, Izack ;
Golany, Boaz ;
Shtub, Avraham .
NETWORKS, 2007, 49 (02) :175-188
[8]  
Demeulemeester E., 2002, Project Scheduling: A Research Handbook
[9]   On the fallacy of averages in project risk management [J].
Elmaghraby, SE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 165 (02) :307-313
[10]   THE ANALYSIS OF ACTIVITY NETWORKS UNDER GENERALIZED PRECEDENCE RELATIONS (GPRS) [J].
ELMAGHRABY, SE ;
KAMBUROWSKI, J .
MANAGEMENT SCIENCE, 1992, 38 (09) :1245-1263