Adaptive genetic algorithms for multi-resource constrained project scheduling problem with multiple modes

被引:0
|
作者
Kim, KwanWoo [1 ]
Gen, Mitsuo
Kim, Myounghun
机构
[1] Tokyo Metropolitan Inst Technol, Dept Intelligent Syst, Tokyo 1900065, Japan
[2] Waseda Univ, Grad Sch Informat Prod & Syst, Kitakyushu, Fukuoka 8080135, Japan
[3] Konkuk Univ, Dept Ind Engn, Seoul 143701, South Korea
来源
INTERNATIONAL JOURNAL OF INNOVATIVE COMPUTING INFORMATION AND CONTROL | 2006年 / 2卷 / 01期
关键词
multi-resource constrained; project scheduling problem; multiple modes; adaptive genetic algorithm;
D O I
暂无
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
In modern manufacturing systems like multi-resource constrained project scheduling problem with the multiple modes (mcPSP-mM) is complicated because of the complex interrelationships between the units of the different stages. In this paper, we develop an adaptive genetic algorithm (aGA) to solve the mcPSP-mM which is a well known NP-hard problem. A new aGA algorithm approach for solving these mcPSP-mM problems is 1) the design of priority-based encoding for activity priority and multistage-based encoding for activity mode, 2) order-based crossover operator for activity priority and local search-based mutation operator for activity mode, 3) iterative hill-climbing method in GA loop, 4) auto-tuning for the rates of crossover and mutation operators. The numerical experiments show that the proposed aGA is effective to the mcPSP-mM.
引用
收藏
页码:41 / 49
页数:9
相关论文
共 50 条
  • [1] Genetic Algorithms for the Resource Constrained Project Scheduling Problem
    Gargiulo, F.
    Quagliarella, D.
    13TH IEEE INTERNATIONAL SYMPOSIUM ON COMPUTATIONAL INTELLIGENCE AND INFORMATICS (CINTI 2012), 2012, : 39 - 47
  • [2] A Resource Constrained Project Scheduling Problem With Multi-Modes
    Altintas, Cansu
    Azizoglu, Meral
    INTERNATIONAL JOURNAL OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT, 2020, 11 (01) : 55 - 70
  • [3] Solving the multi-mode resource-constrained project scheduling problem with genetic algorithms
    Alcaraz, J
    Maroto, C
    Ruiz, R
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2003, 54 (06) : 614 - 626
  • [4] A genetic algorithm for the resource constrained multi-project scheduling problem
    Goncalves, J. F.
    Mendes, J. J. M.
    Resende, M. G. C.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 189 (03) : 1171 - 1190
  • [5] The resource constrained project scheduling problem with multiple crashable modes: A heuristic procedure
    Ahn, T
    Erenguc, SS
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1998, 107 (02) : 250 - 259
  • [6] Characterization of a set of schedules in resource-constrained multi-project scheduling problem with multiple modes
    Artigues, C
    Roubellat, F
    Billaut, JC
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE, 1999, 6 (02): : 112 - 122
  • [7] Application of Petri nets and a genetic algorithm to multi-mode multi-resource constrained project scheduling
    Reddy, JP
    Kumanan, S
    Chetty, OVK
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2001, 17 (04): : 305 - 314
  • [8] Optimized research of resource constrained project scheduling problem based on genetic algorithms
    Li, Xiang
    Kang, Lishan
    Tan, Wei
    ADVANCES IN COMPUTATION AND INTELLIGENCE, PROCEEDINGS, 2007, 4683 : 177 - +
  • [9] Application of Petri Nets and a Genetic Algorithm to Multi-Mode Multi-Resource Constrained Project Scheduling
    J. Prashant Reddy
    S. Kumanan
    O.V. Krishnaiah Chetty
    The International Journal of Advanced Manufacturing Technology, 2001, 17 : 305 - 314
  • [10] A Hybrid Genetic Algorithm for the Resource Constrained Multi-Project Scheduling Problem
    Li, Jinghua
    Liu, Wenjian
    ETFA 2005: 10TH IEEE INTERNATIONAL CONFERENCE ON EMERGING TECHNOLOGIES AND FACTORY AUTOMATION, VOL 2, PROCEEDINGS, 2005,