Minimizing the total completion time on a parallel machine system with tool changes

被引:30
作者
Costa, A. [1 ]
Cappadonna, F. A. [2 ]
Fichera, S. [1 ]
机构
[1] Univ Catania, DII, Dept Ind Engn, I-95124 Catania, Italy
[2] Univ Catania, DIEEI, Dept Informat Elect & Elect Engn, I-95124 Catania, Italy
关键词
Tool change; Unavailability; Metaheuristics; Mixed integer linear programming; Dunn's test; SINGLE-MACHINE; PERIODIC MAINTENANCE; PREVENTIVE MAINTENANCE; IMPROVED APPROXIMATION; 2-MACHINE FLOWSHOP; SCHEDULING PROBLEM; JOBS; MODELS; OPTIMIZATION; ALGORITHM;
D O I
10.1016/j.cie.2015.11.015
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In this paper, the identical parallel machine scheduling problem with periodic tool changes due to wear is addressed under the total completion time minimization objective. Due to machine availability restrictions induced by tool replacement operations, the problem is NP-hard in the strong sense. A mixed integer linear programming (MILP) model has been developed with the aim to provide the global optimum for small-sized test cases. Furthermore, a hybrid metaheuristic procedure based on genetic algorithms has been specifically designed to cope with larger instances. A comprehensive experimental analysis supported by a non-parametric statistical test has been fulfilled to select the best metaheuristic configuration in terms of decoding strategy and parameters driving the search mechanism as well. Then, the proposed optimization procedure has been compared with three alternative methods arising from the relevant literature on the basis of a wide benchmark of test cases. The obtained results, also supported by a proper statistical analysis, demonstrate the effectiveness of the proposed approach for solving the tool change scheduling problem at hand. (C) 2015 Elsevier Ltd. All rights reserved.
引用
收藏
页码:290 / 301
页数:12
相关论文
共 50 条
[11]   Optimization models for the tool change scheduling problem [J].
Chen, Jen-Shiang .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2008, 36 (05) :888-894
[12]   Scheduling of jobs and maintenance in a textile company [J].
Chen, W. J. .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2007, 31 (7-8) :737-742
[13]  
Davis L., 1985, IJCAI, P162
[14]   MULTIPLE COMPARISONS USING RANK SUMS [J].
DUNN, OJ .
TECHNOMETRICS, 1964, 6 (03) :241-&
[15]  
Framinan J M., 2014, Manufacturing Scheduling Systems, DOI DOI 10.1007/978-1-4471-6272-8
[16]  
Gholizadeh Hassan, 2012, Proceedings of the 3rd 2012 International Conference on Industrial Engineering and Operations Management, P806
[17]  
Graves GH, 1999, NAV RES LOG, V46, P845, DOI 10.1002/(SICI)1520-6750(199910)46:7<845::AID-NAV6>3.0.CO
[18]  
2-#
[19]   A SYNTHESIS OF DECISION-MODELS FOR TOOL MANAGEMENT IN AUTOMATED MANUFACTURING [J].
GRAY, AE ;
SEIDMANN, A ;
STECKE, KE .
MANAGEMENT SCIENCE, 1993, 39 (05) :549-567
[20]   Heuristics for minimizing tool switches when scheduling part types on a flexible machine [J].
Hertz, A ;
Laporte, G ;
Mittaz, M ;
Stecke, KE .
IIE TRANSACTIONS, 1998, 30 (08) :689-694