An efficient heuristic for scheduling in a flowshop to minimize total weighted flowtime of jobs

被引:142
|
作者
Rajendran, C [1 ]
Ziegler, H [1 ]
机构
[1] UNIV PASSAU,FAC BUSINESS ADM & ECON,DEPT PROD MANAGEMENT,D-94032 PASSAU,GERMANY
关键词
D O I
10.1016/S0377-2217(96)00273-1
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The problem of scheduling in a flowshop is considered with the objective of minimizing the total weighted flowtime of jobs. A heuristic algorithm is developed by the introduction of lower bounds on the completion times of jobs and the development of heuristic preference relations for the scheduling problem under study. An improvement scheme is incorporated in the heuristic to enhance the quality of its solution. The proposed heuristic, with and without the improvement scheme, and the existing heuristics are evaluated by a large number of randomly generated problems. The results of an extensive computational investigation for various problem sizes are presented. It has been observed that both versions of the proposed heuristic perform better than the existing heuristics in giving a superior solution quality and that the proposed heuristic without the improvement scheme yields a good solution by requiring a negligible CPU time. In addition, an experimental investigation is carried out to evaluate the effectiveness of the improvement scheme when implemented in the proposed heuristic and the existing heuristics, as well as the effectiveness of a variant of the scheme. The results are also discussed. (C) 1997 Elsevier Science B.V.
引用
收藏
页码:129 / 138
页数:10
相关论文
共 50 条
  • [31] A simulated annealing heuristic for scheduling to minimize mean weighted tardiness in a flowshop with sequence-dependent setup times of jobs - A case study
    Parthasarathy, S
    Rajendran, C
    PRODUCTION PLANNING & CONTROL, 1997, 8 (05) : 475 - 483
  • [32] Simulated annealing heuristic for scheduling to minimize mean weighted tardiness in a flowshop with sequence-dependent setup times of jobs - a case study
    Indian Inst of Technology, Madras, India
    Production Planning and Control, 1997, 8 (05): : 475 - 483
  • [33] Scheduling jobs with general linear deterioration to minimize total weighted number of late jobs
    Feng, Yifu
    Geng, Xin-Na
    Lv, Dan-Yang
    Wang, Ji-Bo
    OPTIMIZATION LETTERS, 2024, 18 (05) : 1217 - 1235
  • [34] Column Generation for Sequence Dependent Flowshop Scheduling to Minimize the Total Weighted Tardiness
    Nishi, Tatsushi
    Isoya, Yukinori
    Inuiguchi, Masahiro
    2011 IEEE INTERNATIONAL CONFERENCE ON SYSTEMS, MAN, AND CYBERNETICS (SMC), 2011, : 1187 - 1192
  • [35] Scheduling jobs with general linear deterioration to minimize total weighted number of late jobs
    Yifu Feng
    Xin-Na Geng
    Dan-Yang Lv
    Ji-Bo Wang
    Optimization Letters, 2024, 18 : 1217 - 1235
  • [36] A population-based iterated greedy algorithm to minimize total flowtime for the distributed blocking flowshop scheduling problem
    Chen, Shuai
    Pan, Quan-Ke
    Gao, Liang
    Sang, Hong-yan
    ENGINEERING APPLICATIONS OF ARTIFICIAL INTELLIGENCE, 2021, 104
  • [38] A Genetic Algorithm for Permutation Flowshop Scheduling With Total Flowtime Criterion
    Duan, Jun-Hua
    Zhang, Min
    Qiao, Guang-Yu
    Li, Jun-qing
    2011 CHINESE CONTROL AND DECISION CONFERENCE, VOLS 1-6, 2011, : 1514 - +
  • [39] A Novel Constructive Heuristic for Flowshop Group Scheduling Problems to Minimize Total Flow Time
    He, Xuan
    Liu, Yu-Fan
    Pan, Quan-Ke
    Yu, Yang
    Li, Yuan-Zhen
    2021 PROCEEDINGS OF THE 40TH CHINESE CONTROL CONFERENCE (CCC), 2021, : 1639 - 1644
  • [40] Preemptive scheduling to minimize total weighted late work and weighted number of tardy jobs
    Chen, Rubing
    He, Ruyan
    Yuan, Jinjiang
    COMPUTERS & INDUSTRIAL ENGINEERING, 2022, 167