State extension for adequacy evaluation of composite power systems-applications

被引:38
作者
Billinton, R [1 ]
Zhang, W [1 ]
机构
[1] Univ Saskatchewan, Power Syst Res Grp, Saskatoon, SK S7N 0W0, Canada
关键词
adequacy; power systems; reliability;
D O I
10.1109/59.852155
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
It is not feasible or even possible to investigate all the possible system states of a large practical composite generation and transmission system, as the number of the system states can be extremely large. The probabilities of the normally uninvestigated high level system outage states are individually very small, but the total value can be significant due to the large number of these states. The state extension algorithm can efficiently extend the knowledge of the investigated system states to collectively include the effects of a large number of the uninvestigated system states. The accuracy of the adequacy indices, when using the state extension technique, is therefore improved without investigating the high level system states individually which requires very large computation times. This paper illustrates the effectiveness of the state extension algorithm by application to two reliability test systems, the RBTS, and the IEEE-RTS.
引用
收藏
页码:427 / 432
页数:6
相关论文
共 12 条
  • [1] Development of reliability targets for planning transmission facilities using probabilistic techniques - A utility approach
    Agarwal, SK
    Torre, WV
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 1997, 12 (02) : 704 - 709
  • [2] [Anonymous], 1979, IEEE T POWER AP SYST, V98, P2047, DOI 10.1109/TPAS.1979.319398
  • [3] A RELIABILITY TEST SYSTEM FOR EDUCATIONAL PURPOSES - BASIC DATA
    BILLINTON, R
    KUMAR, S
    CHOWDHURY, N
    CHU, K
    DEBNATH, K
    GOEL, L
    KHAN, E
    KOS, P
    NOURBAKHSH, G
    OTENGADJEI, J
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 1989, 4 (03) : 1238 - 1244
  • [4] Algorithm for failure frequency and duration assessment of composite power systems
    Billinton, R
    Zhang, W
    [J]. IEE PROCEEDINGS-GENERATION TRANSMISSION AND DISTRIBUTION, 1998, 145 (02) : 117 - 122
  • [5] Billinton R., 1984, Reliability Evaluation of Power Systems, DOI DOI 10.1007/978-1-4615-7731-7
  • [6] BILLINTON R, 1998, UNPUB ELECT POWER SY
  • [7] Douglas J., 1994, IEEE Power Engineering Review, V14, P12, DOI 10.1109/39.318697
  • [8] *IEEE APM BULK POW, 1994, IEEE T POWER SYSTEMS, V9, P181
  • [9] APPLICATION OF TRANSMISSION RELIABILITY ASSESSMENT IN PROBABILISTIC PLANNING OF BC-HYDRO VANCOUVER SOUTH METRO SYSTEM
    LI, W
    MANSOUR, Y
    KORCZYNSKI, JK
    MILLS, BJ
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 1995, 10 (02) : 964 - 970
  • [10] Probing the new IEEE Reliability Test System (RTS-96): HL-II assessment
    Pinheiro, JMS
    Dornellas, CRR
    Schilling, MT
    Melo, ACG
    Mello, JCO
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 1998, 13 (01) : 171 - 176