Thaw point

被引:4
作者
Davidson, C. C.
Horwill, C.
De'ry, A.
Granger, M.
机构
[1] Areva T and D and Hydro Québec, AREVA T and D, Hydro, QC
来源
POWER ENGINEER | 2007年 / 21卷 / 06期
关键词
D O I
10.1049/pe:20070606
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Ice accumulation on transmission lines can cause extensive damage to the lines and towers, but a new HVDC solution in Canada that melts the ice has put an end. The HVDC-based de-icer system at the Levis substation is an important aspect of Hydro Quebec TransEnergie's investment programme to reinforce the 735 kV network and minimise the risk of disruption due to ice storms.