Optimal segmentation of projects - Schedule and cost considerations

被引:3
|
作者
Shtub, A [1 ]
Raz, T
机构
[1] TEL AVIV UNIV, SCH ENGN, DEPT IND ENGN, IL-69978 TEL AVIV, ISRAEL
[2] LEON E RECANATI GRAD SCH BUSINESS ADM RAMAT AVIV, FAC MANAGEMENT, IL-69978 TEL AVIV, ISRAEL
关键词
project segmentation; project scheduling; project control; project planning;
D O I
10.1016/0377-2217(95)00260-X
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In certain types of projects, the same sequence of activities is performed throughout the various physical parts of the project (e.g., road construction). By dividing the project into segments and working in parallel, the duration of the project can be reduced, with a resulting increase in direct costs. in this paper we consider the problem of finding the optimal number of segments that minimizes total project cost, for linear cost and duration functions. We begin by formulating and solving a mathematical programming model for homogeneous projects, and, by using the concept of work contents, we extend the solution to non-homogeneous projects.
引用
收藏
页码:278 / 283
页数:6
相关论文
共 46 条
  • [41] Hybrid forecasting modelling of cost and time entities for planning and optimizing projects in the die-cast aluminium industry
    Munoz-Ibanez, C.
    Chairez, I
    Jimenez-Martinez, M.
    Molina, A.
    Alfaro-Ponce, M.
    ADVANCES IN PRODUCTION ENGINEERING & MANAGEMENT, 2023, 18 (02): : 163 - 174
  • [42] Two-Phase Differential Evolution for the Multiobjective Optimization of Time-Cost Tradeoffs in Resource-Constrained Construction Projects
    Cheng, Min-Yuan
    Duc-Hoc Tran
    IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, 2014, 61 (03) : 450 - 461
  • [43] EARLY TARDY COST TRADE-OFFS IN RESOURCE CONSTRAINED PROJECTS WITH CASH FLOWS - AN OPTIMIZATION-GUIDED HEURISTIC APPROACH
    PADMAN, R
    SMITHDANIELS, DE
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1993, 64 (02) : 295 - 311
  • [44] Multimodal optimization for time-cost trade-off in construction projects using a novel hybrid method based on FA and PSO
    Arlbayrak, Gulcag
    Ozdemir, Ilker
    REVISTA DE LA CONSTRUCCION, 2018, 17 (02): : 304 - 318
  • [45] Application of Three Metaheuristic Algorithms to Time-Cost-Quality Trade-Off Project Scheduling Problem for Construction Projects Considering Time Value of Money
    Kebriyaii, Omid
    Heidari, Ali
    Khalilzadeh, Mohammad
    Antucheviciene, Jurgita
    Pavlovskis, Miroslavas
    SYMMETRY-BASEL, 2021, 13 (12):
  • [46] Hybrid NSGA-III and simulated annealing approach for multi-objective time–cost-quality-sustainability optimization in wastewater treatment plant construction projects
    Vijay Kumar
    Lilesh Gautam
    Ritu Dahiya
    Asian Journal of Civil Engineering, 2025, 26 (6) : 2569 - 2584