A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS

被引:21
|
作者
Zhang, Lihui [1 ]
Zou, Xin [1 ]
Qi, Jianxun [1 ]
机构
[1] North China Elect Power Univ, Sch Econ & Management, Beijing 102206, Peoples R China
关键词
Soft logic; repetitive construction projects; time/cost trade-off; scheduling; LINEAR PROJECTS; MODEL; OPTIMIZATION; ALGORITHM; PATH;
D O I
10.3934/jimo.2015.11.1423
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The discrete time/cost trade-off problem (DTCTP) is commonly encountered in repetitive project scheduling. The current models for this problem assume that logical sequences of activities cannot be changed in different units. However, logical sequences are often changed to shorten the project time and minimize project total cost in many practical situations. This characteristic of repetitive activities is referred to as the soft logic. This paper presents a mixed integer nonlinear programming model that combines the general DTCTP and the concept of soft logic. The execution modes of an activity in different units are also considered. The DTCTP is known to be strongly NP-hard, and the introduction of soft logic makes it even more complex. A genetic algorithm (GA) is proposed to resolve the problem. The effectiveness of the proposed GA is verified using the example of a bridge construction project presented in the previous literature. The model proposed in this paper provides more flexibility to reduce the total cost and time of a repetitive project for the planners.
引用
收藏
页码:1423 / 1434
页数:12
相关论文
共 50 条
  • [1] Automated trade-off between time and cost in planning repetitive construction projects
    Hyari, Khalied Hesham
    El-Rayes, Khaled
    El-Mashaleh, Mohammad
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2009, 27 (08) : 749 - 761
  • [2] Mixed-Integer Linear Programming Approach for Scheduling Repetitive Projects with Time-Cost Trade-Off Consideration
    Zou, Xin
    Fang, Shu-Cherng
    Huang, Yuan-Sheng
    Zhang, Li-Hui
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (03)
  • [3] Time-cost-quality trade-off analysis for planning construction projects
    Wang, Tianqi
    Abdallah, Moatassem
    Clevenger, Caroline
    Monghasemi, Shahryar
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (01) : 82 - 100
  • [4] A time - Cost trade-off algorithm for nonserial linear projects
    Senouci, AB
    Eldin, NN
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 1996, 23 (01) : 134 - 149
  • [5] GA Optimization Model for Time/cost Trade-off Problem in Repetitive Projects Considering Resource Continuity
    Zhang, Li-hui
    Zou, Xin
    Su, Zhi-xiong
    APPLIED MATHEMATICS & INFORMATION SCIENCES, 2013, 7 (02): : 611 - 617
  • [6] Bi-Objective Scheduling Optimization for Discrete Time/Cost Trade-Off in Projects
    Li, Hongbo
    Xu, Zhe
    Wei, Wenchao
    SUSTAINABILITY, 2018, 10 (08)
  • [7] Project time-cost trade-off scheduling: a hybrid optimization approach
    Mokhtari, Hadi
    Aghaie, Abdollah
    Rahimi, Javad
    Mozdgir, Ashkan
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 50 (5-8): : 811 - 822
  • [8] Multimode variable resource-constrained time/cost trade-off problem in repetitive projects with adjustment strategy
    Zou, Haobo
    Zhou, Guohua
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (12) : 1271 - 1281
  • [9] TIME-COST TRADE-OFF SCHEDULING UNDER CONSTRUCTION LABOR RESOURCE CONSTRAINTS
    Benjaoran, Vacharapoom
    Sae-Tae, Numpheungk
    SURANAREE JOURNAL OF SCIENCE AND TECHNOLOGY, 2011, 18 (01): : 29 - 39
  • [10] Fuzzy repetitive scheduling for construction projects considering risk preferences and time-cost tradeoffs
    Zou, Xin
    Zhang, Lihui
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2024,