Availability improvement of ITER blanket remote handling system

被引:3
作者
Maruyama, Takahito [1 ]
Mikami, Hidenori [2 ]
Noguchi, Yuto [1 ]
Saito, Makiko [1 ]
Takeda, Nobukazu [1 ]
机构
[1] Natl Inst Quantum & Radiol Sci & Technol, Dept ITER Project, Naka, Ibaraki 3110193, Japan
[2] Toshiba Co Ltd, Isogo Nucl Engn Ctr, Adv Syst Design & Engn Dept, Yokohama, Kanagawa 2358522, Japan
关键词
Remote handling; RAMI; Availability; Reliability; Preventive maintenance;
D O I
10.1016/j.fusengdes.2018.02.049
中图分类号
TL [原子能技术]; O571 [原子核物理学];
学科分类号
0827 ; 082701 ;
摘要
Availability is of the utmost importance in remote-handling systems for fusion reactors. A number of factors are specific to this application in terms of availability. After investigating those factors, we have concluded that preventive maintenance is the best method to universally increase remote handling system availability. As such, we created a procedure through reliability block diagram analysis that takes availability, completion probability, and number of failures into account to determine the parameters for preventive maintenance and determine the quantity of spare parts required. By applying our procedure preventive maintenance increased the availability of the ITER blanket remote handling system from 46% to 88%, while the expected number of total failures was reduced from 5.5 to 1.6. Completion probability remained at virtually 100%, thus demonstrating that our procedure can improve system availability.
引用
收藏
页码:390 / 393
页数:4
相关论文
共 50 条
  • [31] Localization of cask and plug remote handling system in ITER using multiple video cameras
    Ferreira, Joao
    Vale, Alberto
    Ribeiro, Isabel
    FUSION ENGINEERING AND DESIGN, 2013, 88 (9-10) : 1992 - 1996
  • [32] The ITER remote maintenance system
    Tesini, A.
    Palmer, J.
    FUSION ENGINEERING AND DESIGN, 2008, 83 (7-9) : 810 - 816
  • [33] Remote handling assessment of attachment concepts for DEMO blanket segments
    Iglesias, Daniel
    Bastow, Roger
    Cooper, Dave
    Crowe, Robert
    Middleton-Gear, Dave
    Sibois, Romain
    Carloni, Dario
    Vizvary, Zsolt
    Crofts, Oliver
    Harman, Jon
    Loving, Antony
    FUSION ENGINEERING AND DESIGN, 2015, 98-99 : 1500 - 1504
  • [34] Dependability assessment of ITER cask & plug remote handling system during nuclear maintenance operations
    van Houtte, D.
    Elbeze, D.
    Friconneau, J. P.
    Lacroix, C.
    Le Loirec, C.
    Soldaini, M.
    FUSION ENGINEERING AND DESIGN, 2018, 136 : 1342 - 1347
  • [35] Progress in the design, R&D and procurement preparation of the ITER Divertor Remote Handling System
    Esque, Salvador
    van Hille, Carine
    Ranz, Roberto
    Damiani, Carlo
    Palmer, Jim
    Hamilton, David
    FUSION ENGINEERING AND DESIGN, 2014, 89 (9-10) : 2373 - 2377
  • [36] Reliability requirements management for ITER Remote Handling maintenance systems
    Vayrynen, J.
    Mattila, J.
    FUSION ENGINEERING AND DESIGN, 2013, 88 (9-10) : 1920 - 1923
  • [37] Predicting the runtime reliability of ITER Remote Handling maintenance equipment
    Vayrynen, J.
    Mattila, J.
    Vilenius, M.
    Ali, M.
    Valkama, P.
    Siuko, M.
    Semeraro, L.
    FUSION ENGINEERING AND DESIGN, 2011, 86 (9-11) : 2012 - 2015
  • [38] Remote operational trials with the ITER FDR divertor handling equipment
    Irving, M
    Baldi, L
    Benamati, G
    Galbiati, L
    Giacomelli, S
    Lorenzelli, L
    Miccichè, G
    Muro, L
    Polverari, A
    Palmer, J
    Martin, E
    FUSION ENGINEERING AND DESIGN, 2003, 69 (1-4) : 115 - 121
  • [39] Development of a prototype work-cell for validation of ITER remote handling control system standards
    Rastogi, Naveen
    Krishna, Vamshi
    Dutta, Pramit
    Stephen, Manoah
    Gotewal, Krishan Kumar
    Hamilton, David
    Mukherjee, J. K.
    FUSION ENGINEERING AND DESIGN, 2017, 124 : 677 - 681
  • [40] Generic control system design for the Cassette Multifunctional Mover and other ITER remote handling equipment
    Irving, A
    Palmer, J
    Siuko, M
    FUSION ENGINEERING AND DESIGN, 2005, 75-79 : 553 - 557