Fire services installation related contributors of construction delays

被引:11
作者
Fong, NK [1 ]
Wong, LY [1 ]
Wong, LT [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg Serv Engn, Hong Kong, Hong Kong, Peoples R China
关键词
contributors; construction delay; consulting engineers; fire services contractors;
D O I
10.1016/j.buildenv.2005.01.004
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Delay is a common problem in the construction industry and there are several reasons that can contribute to delaying a project. In Hong Kong, completion of fire services installation is prerequisite to completing/finishing a building construction work. The fire services installation must be completed for application of an occupation permit for a building. Fail to obtain the permit on time would lead to construction delay. Apparently, fire services contractors play an important role in obtaining the occuration permit for a project completion. The economic losses due to construction delay could be very significant. This research identified from a list of 49 pre-determined factors in nine categories (shown in Appendix A), the principal factors contributed to construction delays in a fire services installation. In particular, a questionnaire survey of 52 fire services contractors and 32 consulting engineers was conducted in order to obtain their professional judgements about the relative importance of the contributors of construction delay related to the fire services installation. The result showed that the principal contributors were: (1) improper site co-ordination and management of the electrical and mechanical installations, (2) lack of timely decision making of the client, and (3) defects identified during the fire services inspection by local authorities. In addition differing views were found between the consulting engineers and contractors on the areas identified were: (1) site management and supervision, (2) workload of the project staff, (3) the procedures for equipment approval, and (4) working experience of the parties. A monitoring and quality assurance system would be required in these areas to minimize the risk of the probable construction delay. (c) 2005 Elsevier Ltd. All rights reserved.
引用
收藏
页码:211 / 222
页数:12
相关论文
共 14 条
[1]  
Chan D. W. M., 1997, International Journal of Project Management, V15, P55, DOI 10.1016/S0263-7863(96)00039-7
[2]   An evaluation of construction time performance in the building industry [J].
Chan, DWM ;
Kumaraswamy, MM .
BUILDING AND ENVIRONMENT, 1996, 31 (06) :569-578
[3]   RISK MANAGEMENT PERCEPTIONS AND TRENDS OF US CONSTRUCTION [J].
KANGARI, R .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1995, 121 (04) :422-429
[4]   Generic methodology for analyzing delay claims [J].
Kartam, S .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1999, 125 (06) :409-419
[5]  
Kometa ST., 1995, ENG CONSTR ARCHIT MA, V2, P57, DOI [10.1108/eb021003, DOI 10.1108/EB021003]
[6]  
KOMETA TS, 1994, CONSTRUCTION MANAGEM, V12, P433
[7]  
Koushki P. A., 2004, Engineering Construction and Architectural Management, V11, P126, DOI 10.1108/09699980410527867
[8]  
Kumaraiah V, 1998, NIMHANS J, V16, P1
[9]  
Mendenhall W., 1993, LANGUAGE, V17
[10]  
Miller D.C., 1991, HDB RES DESIGN SOCIA