Data-Driven Multi-Energy Investment and Management Under Earthquakes

被引:12
作者
Zhao, Pengfei [1 ,2 ]
Gu, Chenghong [3 ]
Cao, Zhidong [1 ,2 ]
Shen, Yichen [3 ]
Teng, Fei [4 ]
Chen, Xinlei [5 ]
Wu, Chenye [6 ,7 ]
Huo, Da [8 ]
Xu, Xu [9 ]
Li, Shuangqi [3 ]
机构
[1] Chinese Acad Sci, Inst Automat, Beijing 100864, Peoples R China
[2] Univ Chinese Acad Sci, Sch Artificial Intelligence, Beijing 100190, Peoples R China
[3] Univ Bath, Dept Elect & Elect Engn, Bath BA2 7AY, Avon, England
[4] Imperial Coll London, Dept Elect & Elect Engn, London SW7 2AZ, England
[5] Carnegie Mellon Univ, Dept Elect Engn, Pittsburgh, PA 15213 USA
[6] Chinese Univ Hong Kong, Sch Sci & Engn, Hong Kong, Peoples R China
[7] Shenzhen Inst Artificial Intelligence & Robot Soc, Shenzhen 518129, Peoples R China
[8] Newcastle Univ, Sch Engn, Newcastle Upon Tyne NE1 7RU, Tyne & Wear, England
[9] Hong Kong Polytech Univ, Dept Elect Engn, Hong Kong, Peoples R China
基金
中国国家自然科学基金; 英国工程与自然科学研究理事会;
关键词
Economics; Power transmission lines; Uncertainty; Systems operation; Pipelines; Reliability engineering; Transmission line measurements; Distributionally robust optimization (DRO); emergency response; integrated electricity and gas system; reliability; DISTRIBUTION-SYSTEMS; GAS; OPTIMIZATION; ENERGY; RESILIENCE; ELECTRICITY; UNCERTAINTY; STRATEGY; POWER;
D O I
10.1109/TII.2020.3043086
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Seismic events can severely damage both electricity and natural gas systems, causing devastating consequences. Ensuring the secure and reliable operation of the integrated energy system (IES) is of high importance to avoid potential damage to the infrastructure and reduce economic losses. This article proposes a new optimal two-stage optimization to enhance the reliability of IES planning and operation against seismic attacks. In the first stage, hardening investment on the IES is conducted, featuring preventive measures for seismic attacks. The second stage minimizes the expected operation cost of emergency response. The random seismic attack is modeled as uncertainty, which is realized after the first stage. An explicit damage assessment model is developed to define the budget set of the uncertain seismic activity. Based on the survivability of transmission lines and gas pipelines of IES, an optimal system investment plan is developed. The problem is formulated as a two-stage distributionally robust optimization (DRO) model, which is tested on an integrated IEEE 30-bus system and 20-node gas network. Case studies demonstrate that the two-stage DRO outperforms robust optimization and a single-stage optimization model in terms of minimizing the investment cost and expected economic loss. This article can help system operators to make economical hardening and operation strategies to improve the reliability of IES under seismic attacks, thus managing a more robust and secure energy system.
引用
收藏
页码:6939 / 6950
页数:12
相关论文
共 27 条
  • [1] [Anonymous], 2003, HAZUS MH MULTIHAZARD
  • [2] Araneda JuanC., 2010, 2010 Int. Conf. power system technology, P1, DOI [10.1109/POWERCON.2010.5666023, DOI 10.1109/POWERCON.2010.5666023]
  • [3] Optimal inequalities in probability theory: A convex optimization approach
    Bertsimas, D
    Popescu, I
    [J]. SIAM JOURNAL ON OPTIMIZATION, 2005, 15 (03) : 780 - 804
  • [4] Models for Minimax Stochastic Linear Optimization Problems with Risk Aversion
    Bertsimas, Dimitris
    Doan, Xuan Vinh
    Natarajan, Karthik
    Teo, Chung-Piaw
    [J]. MATHEMATICS OF OPERATIONS RESEARCH, 2010, 35 (03) : 580 - 602
  • [5] Integrated Power and Natural Gas Model for Energy Adequacy in Short-Term Operation
    Correa-Posada, Carlos M.
    Sanchez-Martin, Pedro
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2015, 30 (06) : 3347 - 3355
  • [6] Seismic response of buried pipelines: a state-of-the-art review
    Datta, TK
    [J]. NUCLEAR ENGINEERING AND DESIGN, 1999, 192 (2-3) : 271 - 284
  • [7] Distributionally Robust Optimization Under Moment Uncertainty with Application to Data-Driven Problems
    Delage, Erick
    Ye, Yinyu
    [J]. OPERATIONS RESEARCH, 2010, 58 (03) : 595 - 612
  • [8] Eidinger J., P TECHN COUNC LIF EA, P1
  • [9] Robust Network Hardening Strategy for Enhancing Resilience of Integrated Electricity and Natural Gas Distribution Systems Against Natural Disasters
    He, Chuan
    Dai, Chenxi
    Wu, Lei
    Liu, Tianqi
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2018, 33 (05) : 5787 - 5798
  • [10] Hoffman P., 2010, OE ISER FINAL REP OE ISER FINAL REP