Due-date scheduling on parallel machines with job splitting and sequence-dependent major/minor setup times

被引:25
作者
Park, Taeho [1 ]
Lee, Taehyung [1 ]
Kim, Chang Ouk [1 ]
机构
[1] Yonsei Univ, Seoul 120749, South Korea
关键词
Parallel machine scheduling; Due date; Sequence-dependent major/minor setup times; Total tardiness; Job splitting; Heuristics; TARDINESS; PROPERTY; HEURISTICS; ALGORITHM; EARLINESS; COSTS;
D O I
10.1007/s00170-011-3489-x
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
This paper addresses job scheduling problems with parallel machines. To satisfy customers better in a manufacturing company, meeting due dates has been an important performance metric. Besides the numerous other factors affecting due date satisfaction, the splitting of a job through parallel machines can contribute to the reduction of production lead time, resulting in less job tardiness against their due dates. Thus, this paper presents heuristic algorithms for minimizing total tardiness of jobs to meet their due dates in a manufacturing shop with identically functioning machines. The algorithms take into account job splitting and sequence-dependent major/minor setup times. The performance of the proposed heuristics is compared with that of past three algorithms in the literature.
引用
收藏
页码:325 / 333
页数:9
相关论文
共 50 条
[11]   A GENETIC ALGORITHM FOR THE UNRELATED PARALLEL MACHINE SCHEDULING PROBLEM WITH JOB SPLITTING AND SEQUENCE-DEPENDENT SETUP TIMES - LOOM SCHEDULING [J].
Eroglu, Duygu Yilmaz ;
Ozmutlu, H. Cenk ;
Koksal, Seyit Ali .
TEKSTIL VE KONFEKSIYON, 2014, 24 (01) :66-73
[12]   PRODUCTION SCHEDULING WITH SEQUENCE-DEPENDENT SETUPS AND JOB RELEASE TIMES [J].
Montoya-Torres, Jairo R. ;
Soto-Ferrari, Milton ;
Gonzalez-Solano, Fernando .
DYNA-COLOMBIA, 2010, 77 (163) :260-269
[13]   Scheduling unrelated parallel machines with resource-assignable sequence-dependent setup times [J].
Ruiz, Ruben ;
Andres-Romano, Carlos .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2011, 57 (5-8) :777-794
[14]   Branch-and-price approach for robust parallel machine scheduling with sequence-dependent setup times [J].
Yanikoglu, Ihsan ;
Yavuz, Tonguc .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2022, 301 (03) :875-895
[15]   Scheduling unrelated machines with job splitting, setup resources and sequence dependency [J].
Avgerinos, Ioannis ;
Mourtos, Ioannis ;
Vatikiotis, Stavros ;
Zois, Georgios .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2023, 61 (16) :5502-5524
[16]   ABC-based manufacturing scheduling for unrelated parallel machines with machine-dependent and job sequence-dependent setup times [J].
Lin, Shih-Wei ;
Ying, Kuo-Ching .
COMPUTERS & OPERATIONS RESEARCH, 2014, 51 :172-181
[17]   A heuristic algorithm for identical parallel machine scheduling: splitting jobs, sequence-dependent setup times, and limited setup operators [J].
Lee, Jun-Ho ;
Kim, Hyun-Jung .
FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2021, 33 (04) :992-1026
[18]   A heuristic algorithm for identical parallel machine scheduling: splitting jobs, sequence-dependent setup times, and limited setup operators [J].
Jun-Ho Lee ;
Hyun-Jung Kim .
Flexible Services and Manufacturing Journal, 2021, 33 :992-1026
[19]   Bi-criteria formulation for green scheduling with unrelated parallel machines with sequence-dependent setup times [J].
Cota, Luciano P. ;
Coelho, Vitor N. ;
Guimaraes, Frederico G. ;
Souza, Marcone J. F. .
INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2021, 28 (02) :996-1017
[20]   Minimization of maximum lateness on parallel machines with sequence-dependent setup times and job release dates [J].
Lin, Shih-Wei ;
Lee, Zne-Jung ;
Ying, Kuo-Ching ;
Lu, Chung-Cheng .
COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (05) :809-815