Optimal PMU Placement for Complete Power System Observability using Binary Cat Swarm Optimization

被引:0
作者
Srivastava, Ankur [1 ]
Maheswarapu, Sydulu [1 ]
机构
[1] NIT Warangal, Dept Elect Engn, Warangal, Andhra Pradesh, India
来源
2015 INTERNATIONAL CONFERENCE ON ENERGY ECONOMICS AND ENVIRONMENT (ICEEE) | 2015年
关键词
Cat Swarm Optimization; Swarm Intelligence; Phasor Measurement Unit; Observability;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
This paper presents a meta-heuristic algorithm using Binary Cat Swarm Optimization (BCSO). BCSO is binary version of Cat Swarm Optimization (CSO) based on the observation of the behavior of cats. BCSO has two modes of operation: seeking mode and tracing mode. This proposed methodology is used for the optimal placement of phasor measurement units (PMUs) for complete observability of a power system. The objective of this optimization problem is the minimization of the total number of PMUs required by keeping the observability of the system intact. The proposed algorithm was examined with IEEE 14-bus and IEEE 30-bus test system and their results are presented in the paper. These results were also verified with different existing conventional and meta-heuristic algorithms such as binary particle swarm optimization, generalized integer linear programming and effective data structure based algorithm. It is first time that the proposed binary cat swarm optimization has been contemplated for the problem of optimal placement of PMUs.
引用
收藏
页数:6
相关论文
共 50 条
  • [31] Economic Analysis of a Power System Network using Optimal Placement of PMUs and DULRs Through Complete and Incomplete Observability Analysis
    Bala Krishna, K.
    Rachananjali, K.
    Mercy Rosalina, K.
    Srinivasa Rao, Y.
    JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY, 2021, 16 (01) : 55 - 66
  • [32] Economic Analysis of a Power System Network using Optimal Placement of PMUs and DULRs Through Complete and Incomplete Observability Analysis
    K. Bala Krishna
    K. Rachananjali
    K. Mercy Rosalina
    Y. Srinivasa Rao
    Journal of Electrical Engineering & Technology, 2021, 16 : 55 - 66
  • [33] Weak bus-constrained PMU placement for complete observability of a connected power network considering voltage stability indices
    Babu, Rohit
    Raj, Saurav
    Bhattacharyya, Biplab
    PROTECTION AND CONTROL OF MODERN POWER SYSTEMS, 2020, 5 (01)
  • [34] A Clustering Based Approach for Observability and Controllability Analysis for Optimal Placement of PMU
    Murthy, Ch
    Mohanta, D. K.
    MahendraMeher
    INTERNATIONAL CONFERENCE ON MATERIALS, ALLOYS AND EXPERIMENTAL MECHANICS (ICMAEM-2017), 2017, 225
  • [35] Optimal placement of phasor measurement units for power system observability
    Chakrabarti, Saikat
    Kyriakides, Elias
    IEEE TRANSACTIONS ON POWER SYSTEMS, 2008, 23 (03) : 1433 - 1440
  • [36] Optimal Phasor Measuring Unit Placement by Binary Particle Swarm Optimization
    Kumari, Saroj
    Walde, Pratima
    Iqbal, Asif
    Tyagi, Akash
    2017 8TH INTERNATIONAL CONFERENCE ON COMPUTING, COMMUNICATION AND NETWORKING TECHNOLOGIES (ICCCNT), 2017,
  • [37] Binary Cat Swarm Optimization for Cryptanalysis
    Amic, Seeven
    Soyjaudah, K. M. Sunjiv
    Ramsawock, Gianeshwar
    2017 IEEE INTERNATIONAL CONFERENCE ON ADVANCED NETWORKS AND TELECOMMUNICATIONS SYSTEMS (ANTS), 2017,
  • [38] Simplified binary cat swarm optimization
    Siqueira, Hugo
    Santana, Clodomir
    Macedo, Mariana
    Figueiredo, Elliackin
    Gokhale, Anuradha
    Bastos-Filho, Carmelo
    INTEGRATED COMPUTER-AIDED ENGINEERING, 2021, 28 (01) : 35 - 50
  • [39] Reliability-constrained Based Optimal Placement and Sizing of Multiple Distributed Generators in Power Distribution Network Using Cat Swarm Optimization
    Kumar, Deepak
    Samantaray, S. R.
    Kamwa, I.
    Sahoo, N. C.
    ELECTRIC POWER COMPONENTS AND SYSTEMS, 2014, 42 (02) : 149 - 164
  • [40] A Multi-objective PMU Placement Method in Power System via Binary Gravitational Search Algorithm
    Singh, Satyendra Pratap
    Singh, Shiv Pujan
    ELECTRIC POWER COMPONENTS AND SYSTEMS, 2017, 45 (16) : 1832 - 1845