Making formwork construction lean

被引:44
作者
Ko, Chien-Ho [1 ]
Kuo, Jiun-De [2 ]
机构
[1] Natl Pingtung Univ Sci & Technol, Dept Civil Engn, Neipu 91201, Pingtung, Taiwan
[2] Taiwan Construct Res Inst, Informat Ctr Construct Ind, Taipei, Taiwan
关键词
andon; formwork; kanban; lean manufacturing; PRECAST FABRICATION; CONCRETE; MODEL;
D O I
10.3846/13923730.2014.890655
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Formwork material and payroll are among the greatest costs in building reinforced concrete structures. Therefore, formwork engineering is a key factor affecting project success. Traditional formwork construction entails non-value-adding activities resulting in waste. The objective of this study is to adapt lean manufacturing techniques to formwork engineering in a bid to reduce waste, specifically by developing a lean formwork construction model. In the model, andon is used to establish an on-site quality control culture, allowing form workers to obtain assistance immediately whenever a problem occurs. In addition, formwork operations are pulled through the kanban system to reduce mould inventory and achieve continuous construction flow. A case study is used to validate the applicability of the proposed model. Results show that the proposed model can effectively reduce waste in the formwork construction flow and increase the value of operations, thus providing a new approach to improving formwork engineering.
引用
收藏
页码:444 / 458
页数:15
相关论文
共 50 条
[21]   Trends and gaps in lean construction practices for construction of megaprojects: A critical review [J].
Ibrahim, Abdelazim ;
Zayed, Tarek ;
Lafhaj, Zoubeir .
ALEXANDRIA ENGINEERING JOURNAL, 2025, 118 :174-193
[22]   Application of Sensitivity Analysis for Multiple Attribute Decision Making in Lean Production System [J].
Singh, Sarbrinder Paul ;
Mehta, Amrinder ;
Vasudev, Hitesh .
ENGINEERING MANAGEMENT JOURNAL, 2025, 37 (04) :390-413
[23]   Implementing lean construction to improve quality and megaproject construction: a case study [J].
Idrissi Gartoumi, Khalil ;
Aboussaleh, Mohamed ;
Zaki, Smail .
JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2024, 29 (01) :1-22
[24]   Lean management in the context of construction supply chains [J].
Meng, Xianhai .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2019, 57 (11) :3784-3798
[25]   The role of artificial intelligence in lean construction management [J].
Dumrak, Jantanee ;
Zarghami, Seyed Ashkan .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2025, 32 (01) :131-155
[26]   Factors in formwork selection: a comparative investigation [J].
Proverbs, DG ;
Holt, GD ;
Olomolaiye, PO .
BUILDING RESEARCH AND INFORMATION, 1999, 27 (02) :109-119
[27]   Level of awareness of formwork design in the Ghanaian construction industry; enabling future technology application [J].
Boakye Danquah, Clement ;
Acheampong, Alex ;
Adjei-Kumi, Theophilus .
JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2022, 20 (04) :1015-1039
[28]   Investigating the Impact of Lean Leadership on Construction Project Success [J].
Sadikoglu, Emel ;
Jaeger, Jonathan ;
Demirkesen, Sevilay ;
Baier, Carolin ;
Oprach, Svenja ;
Haghsheno, Shervin .
ENGINEERING MANAGEMENT JOURNAL, 2024, 36 (02) :206-220
[29]   Readiness Factors for Sustainable Lean Transformation of Construction Organizations [J].
Prasad, Kudrekodlu V. ;
Vasugi, Venkatesan .
SUSTAINABILITY, 2023, 15 (08)
[30]   Organisational culture in lean construction: managing paradoxes and dilemmas [J].
Erthal, Alice ;
Marques, Leonardo .
PRODUCTION PLANNING & CONTROL, 2022, 33 (11) :1078-1096