AN EARNED-VALUE-ANALYSIS (EVA)-BASED PROJECT CONTROL FRAMEWORK IN LARGE-SCALE SCAFFOLDING PROJECTS USING LINEAR REGRESSION MODELING

被引:2
作者
Lei, Zhen [1 ]
Hu, Yongde [2 ]
Hua, Jialiang [2 ]
Marton, Brandon [3 ]
Goldberg, Peter [4 ]
Marton, Noah [4 ]
机构
[1] Univ New Brunswick, Dept Civil Engn, Off Site Construct, Fredericton, NB, Canada
[2] Univ New Brunswick, Fac Comp Sci, Fredericton, NB, Canada
[3] Hinton Scaffold Solut, Business Dev, Toronto, ON, Canada
[4] Hinton Scaffold Solut, Toronto, ON, Canada
来源
JOURNAL OF INFORMATION TECHNOLOGY IN CONSTRUCTION | 2022年 / 27卷
基金
加拿大自然科学与工程研究理事会;
关键词
scaffolding management; regression models; project control; earned-value analysis;
D O I
10.36680/j.itcon.2022.031
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In large-scale industrial construction projects, scaffolding activities account for a large amount of the construction budget, and overlooking the scaffolding management can lead to budget overruns and schedule delays. The scaffolding activities can be categorized by classifications and types based on the nature of the scaffold builds. To ensure the project progress on track, it is critical to measure project performance based on project progress data. However, given the nature of scaffolding activities, it has been challenging to track and utilize the scaffolding data for analytical purposes. Therefore, this paper proposes a project control framework based on Earned-value analysis (EVA), in which linear regression models are used for productivity prediction. Three scenarios of productivity based on historical data (i.e., low, medium, and high productivity) are introduced. The proposed framework is implemented in a real construction project for validation. The results have shown that the proposed framework can efficiently evaluate the project progresses integrated with the EVA. The construction companies, such as general contractors and scaffolding sub-contractors, can use this method for site progress tracking. For future work, the EVA can be integrated with other non-linear predictive models (e.g., neural network) for productivity prediction. The EVA results can be integrated with data visualization to create situational awareness for construction practitioners.
引用
收藏
页码:630 / 641
页数:12
相关论文
共 20 条
  • [1] A simulation-based approach for material yard laydown planning
    Alanjari, Pejman
    Razavialavi, Seyedreza
    AbouRizk, Simaan
    [J]. AUTOMATION IN CONSTRUCTION, 2014, 40 : 1 - 8
  • [2] Predictive Modeling of Workplace Stress among Construction Professionals
    Bowen, Paul
    Edwards, Peter
    Lingard, Helen
    Cattell, Keith
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (03)
  • [3] Data-driven predictive maintenance planning framework for MEP components based on BIM and IoT using machine learning algorithms
    Cheng, Jack C. P.
    Chen, Weiwei
    Chen, Keyu
    Wang, Qian
    [J]. AUTOMATION IN CONSTRUCTION, 2020, 112 (112)
  • [4] Data-Driven Monitoring System for Preventing the Collapse of Scaffolding Structures
    Cho, Chunhee
    Kim, Kyungki
    Park, JeeWoong
    Cho, Yong K.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (08)
  • [5] Discrete Firefly Algorithm for Scaffolding Construction Scheduling
    Hou, Lei
    Zhao, Chuanxin
    Wu, Changzhi
    Moon, Sungkon
    Wang, Xiangyu
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (03)
  • [6] Howes R., 2000, ENG CONSTR ARCHIT MA, V7, P399
  • [7] Data-Driven Simulation Model for Quality-Induced Rework Cost Estimation and Control Using Absorbing Markov Chains
    Ji, Wenying
    AbouRizk, Simaan M.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (08)
  • [8] Semiautomated Scaffolding Planning: Development of the Feature Lexicon for Computer Application
    Kim, Jonghoon
    Fischer, Martin
    Kunz, John
    Levitt, Raymond
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2015, 29 (05)
  • [9] Integrating work sequences and temporary structures into safety planning: Automated scaffolding-related safety hazard identification and prevention in BIM
    Kim, Kyungki
    Cho, Yong
    Zhang, Sijie
    [J]. AUTOMATION IN CONSTRUCTION, 2016, 70 : 128 - 142
  • [10] Automatic design and planning of scaffolding systems using building information modeling
    Kim, Kyungki
    Teizer, Jochen
    [J]. ADVANCED ENGINEERING INFORMATICS, 2014, 28 (01) : 66 - 80