Real-time scheduling of multi-stage flexible job shop floor

被引:24
|
作者
Ham, Myoungsoo [1 ]
Lee, Young Hoon [2 ]
Kim, Sun Hoon [2 ]
机构
[1] Samsung Austin Semicond, Syst Engn, Austin, TX USA
[2] Yonsei Univ, Dept Informat & Ind Engn, Seoul 120749, South Korea
关键词
job shop; integer programming; multi-stage; optimisation; real-time; scheduling; BATCH PLANTS; FORMULATION; ALGORITHMS; MACHINES; MODELS; SYSTEM;
D O I
10.1080/00207543.2010.492797
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper first formulates a binary integer programming (BIP) model that minimises Cmax for a multi-stage flexible job shop floor with machine compatibility. Due to a computational limitation, the exact optimal model is then relaxed as a linear programming model. The output from the relaxation model then turns into the objective of the BIP-based real-time scheduling (RTS) heuristic model. The RTS heuristic requires an iteration to calculate the final Cmax. At each iteration, the RTS heuristic assigns just one job to the earliest available machines. Since the set of jobs and machines included in the RTS model is relatively small, RTS can be solved in a very short computational time. We evaluate an overall effectiveness (in terms of solution quality and run time) of the RTS heuristic by way of computer experiments.
引用
收藏
页码:3715 / 3730
页数:16
相关论文
共 50 条
  • [31] REAL-TIME JOB SHOP SCHEDULING BASED ON SIMULATION AND MARKOV DECISION PROCESSES
    Zhang, Tao
    Xie, Shufang
    Rose, Oliver
    2017 WINTER SIMULATION CONFERENCE (WSC), 2017, : 3899 - 3907
  • [32] Simulated Annealing Algorithm for Job Shop Scheduling on Reliable Real-Time Systems
    Zorin, Daniil A.
    Kostenko, Valery A.
    OPERATIONS RESEARCH AND ENTERPRISE SYSTEMS, ICORES 2014, 2015, 509 : 31 - 46
  • [33] Real-Time Selection System of Dispatching Rules for the Job Shop Scheduling Problem
    Zhao, Anran
    Liu, Peng
    Li, Yunfeng
    Xie, Zheyu
    Hu, Longhao
    Li, Haoyuan
    MACHINES, 2023, 11 (10)
  • [34] Digital twin and deep reinforcement learning enabled real-time scheduling for complex product flexible shop-floor
    Chang, Xiao
    Jia, Xiaoliang
    Fu, Shifeng
    Hu, Hao
    Liu, Kuo
    PROCEEDINGS OF THE INSTITUTION OF MECHANICAL ENGINEERS PART B-JOURNAL OF ENGINEERING MANUFACTURE, 2023, 237 (08) : 1254 - 1268
  • [35] Deep reinforcement learning based AGVs real-time scheduling with mixed rule for flexible shop floor in industry 4.0
    Hu, Hao
    Jia, Xiaoliang
    He, Qixuan
    Fu, Shifeng
    Liu, Kuo
    COMPUTERS & INDUSTRIAL ENGINEERING, 2020, 149
  • [36] Real-time shop floor integration, simplified
    IQMS
    Rubber World, 2008, 2 (21-22+31):
  • [37] REAL-TIME AUTOMATED SHOP FLOOR CONTROL
    MURAKAMI, W
    JOURNAL OF THE ELECTROCHEMICAL SOCIETY, 1987, 134 (8B) : C449 - C449
  • [38] EFFICIENT ALGORITHMS FOR THE MULTI-STAGE FLEXIBLE FLOW SHOP SCHEDULING PROBLEM WITH TRANSPORTATION AND UNLOADING TIMES
    Hidri, Lotfi
    Tlija, Mehdi
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE, 2024, 31 (04): : 709 - 733
  • [39] A genetic algorithm for job shop scheduling in real time
    Wu, ZM
    Zhao, CW
    PROCEEDINGS OF THE 1997 AMERICAN CONTROL CONFERENCE, VOLS 1-6, 1997, : 162 - 163
  • [40] An effective hybrid multi objective evolutionary algorithm for solving real time event in flexible job shop scheduling problem
    Reddy, M. B. S. Sreekara
    Ratnam, Ch.
    Rajyalakshmi, G.
    Manupati, V. K.
    MEASUREMENT, 2018, 114 : 78 - 90