Delay Risk Assessment of Repetitive Construction Projects Using Line-of-Balance Scheduling and Monte Carlo Simulation

被引:46
作者
Tokdemir, Onur B. [1 ]
Erol, Huseyin [1 ]
Dikmen, Irem [1 ]
机构
[1] Middle East Tech Univ, Dept Civil Engn, TR-06800 Ankara, Turkey
关键词
Delay risk assessment; Line-of-balance (LOB) scheduling; Monte Carlo simulation; Repetitive projects; Construction management; COMPLEXITY;
D O I
10.1061/(ASCE)CO.1943-7862.0001595
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Although the line-of-balance (LOB) method is widely used for the scheduling of repetitive construction projects, there are only a limited number of studies that deal with the issue of how to incorporate uncertainty in repetitive schedules. In this paper, a delay risk assessment method is proposed for projects scheduled by LOB. In the proposed method, a LOB schedule is prepared considering the target rate of delivery, and then risk scenarios are defined considering the sources of uncertainty and vulnerability of activities. Next, probability distributions are determined for the required number of labor-hours for each activity and for learning rates, and finally, the delay risk of the project is quantified using Monte Carlo simulation. The application of the method, its outputs, and its potential benefits are demonstrated by a hypothetical case study. Moreover, the proposed method is applied to a real high-rise building project and the potential benefits of using a probabilistic LOB schedule at the planning stage are investigated. The findings reveal that the outputs of the proposed method may enable decision makers to estimate delay risk under various scenarios, formulate effective risk response strategies, and prepare contingency plans for resource utilization in repetitive tasks. However, the simplifying assumptions made during the development of the proposed model regarding the relationships between activity durations, risk scenarios, and learning rates may limit its applicability for all project conditions. Yet the method is generic, and its assumptions can be revised in consideration of specific project characteristics and objectives.
引用
收藏
页数:12
相关论文
共 34 条
  • [21] Defining uncertainty in projects - a new perspective
    Perminova, Olga
    Gustafsson, Magnus
    Wikström, Kim
    [J]. International Journal of Project Management, 2008, 26 (01) : 73 - 79
  • [22] Project Complexity and Risk Management (ProCRiM): Towards modelling project complexity driven risk paths in construction projects
    Qazi, Abroon
    Quigley, John
    Dickson, Alex
    Kirytopoulos, Konstantinos
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (07) : 1183 - 1198
  • [23] Sacks R, 2017, CONSTR MANAG ECON, V35, P45, DOI 10.1080/01446193.2016.1274417
  • [24] Genetic algorithm-based multi-objective model for scheduling of linear construction projects
    Senouci, Ahmed
    Al-Derham, Hassan R.
    [J]. ADVANCES IN ENGINEERING SOFTWARE, 2008, 39 (12) : 1023 - 1028
  • [25] SRA, 2015, SRA GLOSS
  • [26] Srisuwanrat Chachrist, 2007, 2007 Winter Simulation Conference, P2151, DOI 10.1109/WSC.2007.4419849
  • [27] Strategic Analysis and Estimating Office, 2018, PROJECT RISK MANAGEM
  • [28] Similarities and contrasts of complexity, uncertainty, risks, and resilience in supply chains and temporary multi-organization projects
    Tavares Thome, Antonio Marcio
    Scavarda, Luiz Felipe
    Scavarda, Annibal
    Sydio de Souza Thome, Felipe Eduardo
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (07) : 1328 - 1346
  • [29] ALISS: Advanced Linear Scheduling System
    Tokdemir, Onur B.
    Arditi, David
    Balcik, Cenk
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2006, 24 (12) : 1253 - 1267
  • [30] JUDGMENT UNDER UNCERTAINTY - HEURISTICS AND BIASES
    TVERSKY, A
    KAHNEMAN, D
    [J]. SCIENCE, 1974, 185 (4157) : 1124 - 1131