Delay Risk Assessment of Repetitive Construction Projects Using Line-of-Balance Scheduling and Monte Carlo Simulation

被引:46
作者
Tokdemir, Onur B. [1 ]
Erol, Huseyin [1 ]
Dikmen, Irem [1 ]
机构
[1] Middle East Tech Univ, Dept Civil Engn, TR-06800 Ankara, Turkey
关键词
Delay risk assessment; Line-of-balance (LOB) scheduling; Monte Carlo simulation; Repetitive projects; Construction management; COMPLEXITY;
D O I
10.1061/(ASCE)CO.1943-7862.0001595
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Although the line-of-balance (LOB) method is widely used for the scheduling of repetitive construction projects, there are only a limited number of studies that deal with the issue of how to incorporate uncertainty in repetitive schedules. In this paper, a delay risk assessment method is proposed for projects scheduled by LOB. In the proposed method, a LOB schedule is prepared considering the target rate of delivery, and then risk scenarios are defined considering the sources of uncertainty and vulnerability of activities. Next, probability distributions are determined for the required number of labor-hours for each activity and for learning rates, and finally, the delay risk of the project is quantified using Monte Carlo simulation. The application of the method, its outputs, and its potential benefits are demonstrated by a hypothetical case study. Moreover, the proposed method is applied to a real high-rise building project and the potential benefits of using a probabilistic LOB schedule at the planning stage are investigated. The findings reveal that the outputs of the proposed method may enable decision makers to estimate delay risk under various scenarios, formulate effective risk response strategies, and prepare contingency plans for resource utilization in repetitive tasks. However, the simplifying assumptions made during the development of the proposed model regarding the relationships between activity durations, risk scenarios, and learning rates may limit its applicability for all project conditions. Yet the method is generic, and its assumptions can be revised in consideration of specific project characteristics and objectives.
引用
收藏
页数:12
相关论文
共 34 条
  • [1] Multi-objective genetic optimization for scheduling a multi-storey building
    Agrama, Fatma A.
    [J]. AUTOMATION IN CONSTRUCTION, 2014, 44 : 119 - 128
  • [2] Modeling of LOB scheduling with learning development effect
    Ammar, Mohammad A.
    Abdel-Maged, Amena F.
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2018, 18 (06) : 517 - 526
  • [3] Effect of learning on line-of-balance scheduling
    Arditi, David
    Tokdemir, Onur Behzat
    Suh, Kangsuk
    [J]. International Journal of Project Management, 2001, 19 (05) : 265 - 277
  • [4] Challenges in line-of-balance scheduling
    Arditi, D
    Tokdemir, OB
    Suh, K
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2002, 128 (06): : 545 - 556
  • [5] LINE-OF-BALANCE SCHEDULING IN PAVEMENT CONSTRUCTION
    ARDITI, D
    ALBULAK, MZ
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03): : 411 - 424
  • [6] Arditi D., 2002, Construction Management and Economics, V20, P353, DOI DOI 10.1080/01446190210131647
  • [7] Clarifying the project complexity construct: Past, present and future
    Bakhshi, Javad
    Ireland, Vernon
    Gorod, Alex
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (07) : 1199 - 1213
  • [8] Impacts of different objective functions on resource leveling in Line-of-Balance scheduling
    Damci, Atilla
    Arditi, David
    Polat, Gul
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2016, 20 (01) : 58 - 67
  • [9] Resource Leveling in Line-of-Balance Scheduling
    Damci, Atilla
    Arditi, David
    Polat, Gul
    [J]. COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2013, 28 (09) : 679 - 692
  • [10] Multiresource Leveling in Line-of-Balance Scheduling
    Damci, Atilla
    Arditi, David
    Polat, Gul
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (09) : 1108 - 1116