Process reengineering and improvement for building precast production

被引:45
作者
Chen, Jieh-Haur [1 ]
Yang, Li-Ren [2 ]
Tai, Hsing-Wei [1 ]
机构
[1] Natl Cent Univ, Inst Construct Engn & Management, Taoyuan 32001, Taiwan
[2] Tamkang Univ, Dept Business Adm, Taipei 25137, Taiwan
关键词
Precast process; Reengineering; Simulation; Productivity; Construction engineering; SIMULATION; FREIGHT;
D O I
10.1016/j.autcon.2016.05.015
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Current production methods for the building of precast concrete elements are gradually becoming insufficient to meet industry demands. Most precast factories incorporate fixed molding production lines to produce building structural elements such as beams, trabeculae and pillars. Improvement of current production has reached its limits. The objective of this study is to perform process reengineering so as to create more efficient precast processes. The results of the literature review and advice from 16 experts suggest that the current process used to produce a precast element, which is comprised of 16 steps in a single module, should be redesigned to include 13 steps in 3 modules. Using historical data as input, the Arena software, Version 13, is adopted to simulate both the traditional and proposed methods, and then compare the results for practicability. An overall savings of production time of 24% can be reached by changing the current/traditional method to the flow-shop type production method. (C) 2016 Elsevier B.V. All rights reserved.
引用
收藏
页码:249 / 258
页数:10
相关论文
共 27 条
[1]  
Bush A., 1751, P 35 C WINT SIM DRIV
[2]   Constraint programming approach to-precast production scheduling [J].
Chan, WT ;
Hu, H .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2002, 128 (06) :513-521
[3]   An application of genetic algorithms to precast production scheduling [J].
Chan, WT ;
Hu, H .
COMPUTERS & STRUCTURES, 2001, 79 (17) :1605-1616
[4]   Simulation of freight traffic in the Seville inland port [J].
Cortes, Pablo ;
Munuzuri, Jesus ;
Ibanez, J. Nicolas ;
Guadiz, Jose .
SIMULATION MODELLING PRACTICE AND THEORY, 2007, 15 (03) :256-271
[5]  
Davenport T., 1990, Sloan Management Review
[6]   A cost optimization-based design of precast concrete floors using genetic algorithms [J].
de Albuquerque, Augusto T. ;
El Debs, Mounir K. ;
Melo, Antonio M. C. .
AUTOMATION IN CONSTRUCTION, 2012, 22 :348-356
[7]  
HAMMER M, 1990, HARVARD BUS REV, V68, P104
[8]  
Hammer M., 1994, REENGINEERING CORPOR
[9]  
Johansson H.J., 1993, Business Process Reengineering: Break Point Strategies for Market Dominance
[10]  
Kabilan V, 2005, P CAISE 2005 WORKSH, P557