Incorporating demand response effect on transformer replacement planning

被引:2
作者
Moghadami, Arash [1 ]
Azizian, Davood [2 ]
Karimi, Amin [1 ]
机构
[1] Islamic Azad Univ, Elect Engn Dept, Sanandaj Branch, Sanandaj, Iran
[2] Islamic Azad Univ, Elect Engn Dept, Abhar Branch, Abhar, Iran
关键词
Demand response; Failure rate; Reliability; And transformer replacement planning; CONGESTION; IMPACTS; IMPROVE; SYSTEM;
D O I
10.1016/j.epsr.2022.108714
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
Transformer replacement planning is a long-term optimization problem of power system engineering. Therefore, long-term effects as loading and ageing should be considered in the problem. The most crucial reason in such a long term problem in power system is reliability issues. Accordingly, in this paper, long-term effect of loading on transformer failure rates has been modelled and demand response (DR) has been implemented to reduce loading rate of the system. In order to optimize effectiveness of DR, its implementation cost has been added to the objective function of the problem. In addition, reducing the failure rate of existing transformer may decrease the need for a new transformer so that the reliability of the system has a desirable level. On the other hand, a decrease in existing transformer loading rate in the long run, makes them more valuable at the end of the planning horizon. Hence, the value of transformers should be embedded in the objective function. Additionally, reducing loading rate causes lower loss of load at contingencies caused by transformers from two point of view, first reduced failure rate and second reduced peak load. The developed model has been implemented on transformers of THE IEEE 24-bus reliability test system (IEEE RTS) in two case studies. Results show DR can enhance network performance technically by increasing network reliability and decreasing transformer loading and can improve network operation economically by decreasing operational and expansion costs
引用
收藏
页数:7
相关论文
共 50 条
  • [41] Distribution Network Reinforcement Planning Considering Demand Response Support
    Cesena, Eduardo Alejandro Martinez
    Mancarella, Pierluigi
    2014 POWER SYSTEMS COMPUTATION CONFERENCE (PSCC), 2014,
  • [42] Distributed Generation and Demand Response Effects on the Distribution Network Planning
    Rey, Marcelo
    Montes de Oca, Sebastian
    Giusto, Alvaro
    Vignolo, Mario
    PROCEEDINGS OF THE 2018 IEEE PES TRANSMISSION & DISTRIBUTION CONFERENCE AND EXHIBITION - LATIN AMERICA (T&D-LA), 2018,
  • [43] Transformer Management System for Energy Control of Customer Demand Response and PV Systems
    Ku, Te-Tien
    Chen, Chao-Shun
    Lin, Chia-Hung
    Hsu, Cheng-Ting
    Chuang, Hui-Jen
    IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, 2019, 55 (01) : 51 - 59
  • [44] Transformer Management System for Energy Control of Customer Demand Response and PV Systems
    Ku, T. T.
    Chen, C. S.
    Lin, C. H.
    Hsu, C. T.
    2017 IEEE INDUSTRY APPLICATIONS SOCIETY ANNUAL MEETING, 2017,
  • [45] Affine decision rule approximation to address demand response uncertainty in smart Grids? capacity planning
    Sani, Sajad Aliakbari
    Bahn, Olivier
    Delage, Erick
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2022, 303 (01) : 438 - 455
  • [46] Distribution network planning method using demand response resources
    Lan, Li
    Zhang, Mingze
    Yang, Jianlin
    Qin, Kuangyu
    Zhang, Mengyao
    Ji, Yuan
    Fei, Fei
    Wang, Haiqun
    2018 CHINA INTERNATIONAL CONFERENCE ON ELECTRICITY DISTRIBUTION (CICED), 2018, : 2641 - 2644
  • [47] Integrated resources planning in microgrid based on modeling demand response
    Zhu, Lan
    Yan, Zheng
    Yang, Xiu
    Fu, Yang
    Zhongguo Dianji Gongcheng Xuebao/Proceedings of the Chinese Society of Electrical Engineering, 2014, 34 (16): : 2621 - 2628
  • [48] Simulation and evaluation of multicriteria planning heuristics for demand response in datacenters
    Murana, Jonathan
    Nesmachnow, Sergio
    SIMULATION-TRANSACTIONS OF THE SOCIETY FOR MODELING AND SIMULATION INTERNATIONAL, 2023, 99 (03): : 291 - 310
  • [49] Reliability evaluation incorporating Demand Response and Time varying thermal Ratings of OHLs
    Abogaleela, Mohamed
    Kopsidas, Konstantinos
    2018 TWENTIETH INTERNATIONAL MIDDLE EAST POWER SYSTEMS CONFERENCE (MEPCON), 2018, : 1069 - 1074
  • [50] Demand Response Coupled with Dynamic Thermal Rating for Increased Transformer Reserve and Lifetime
    Daminov, Ildar
    Rigo-Mariani, Remy
    Caire, Raphael
    Prokhorov, Anton
    Alvarez-Herault, Marie-Cecile
    ENERGIES, 2021, 14 (05)