Application of geographic information systems in construction safety planning

被引:119
作者
Bansal, V. K. [1 ]
机构
[1] Natl Inst Technol NIT Hamirpur, Dept Civil Engn, Hamirpur 177005, Himachal Prades, India
关键词
4D; Construction management; Construction safety; GIS; GIS; SCHEDULE; BEHAVIOR; CULTURE; LAYOUT; MODEL; RISK; TOOL;
D O I
10.1016/j.ijproman.2010.01.007
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Execution schedule and 2D drawings are generally used for hazards identification in the construction safety planning process. Planner visualises 2D drawings into a 3D model and mentally links its components with the respective activities defined in the schedule to understand the execution sequence in safety planning. Sequence interpretation and accordingly the hazards identification vary with the level of experience, knowledge and individual perspective of the safety planner. Therefore, researchers suggest the use of four dimensional (4D) modelling or building information modelling (BIM) to create the simulation of construction process by linking execution schedule with the 3D model. Both however lack in the features like: generation and updating of schedule, 3D components editing, topography modelling and geospatial analysis within a single platform which is now a major requirement of the construction industry. This work facilitates 4D modelling, geospatial analysis and topography modelling in the development of safe execution sequence by using geographic information systems (GIS), both 3D model along with its surrounding topography and schedule were developed and linked together within the same environment. During safety review process if planned sequence results a hazard situation, it may be corrected within the GIS itself before actual implementation. Paper also discusses the use of GIS in the development of safety database from which safety information are retrieved and linked with the activities of the schedule or components of a building model. 4D modelling along with topographical conditions and safety database in a single environment assist safety planner in examining what safety measures are required when, where and why. Developed methodology was tested on a real life project in India, lessons learned from the implementation have been discussed in the potential benefits and limitations section. At last, paper highlights major research areas for further improvements. (c) 2010 Elsevier Ltd and IPMA. All rights reserved.
引用
收藏
页码:66 / 77
页数:12
相关论文
共 39 条
  • [1] Analysis of a safety planning and control model from the human error perspective
    Abreu Saurin, Tarcisio
    Torres Formoso, Carlos
    Borges Cambraia, Fabricio
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2005, 12 (03) : 283 - +
  • [2] [Anonymous], 4D CAD VISUALIZATION
  • [3] Aouald G, 2007, CONSTRUCTION FUTURE
  • [4] ArcGIS version 9 Introduction part I & II, 2004, ARCGIS VERS 9 INTR 1
  • [5] Generating, evaluating, and visualizing construction schedule with geographic information systems
    Bansal, V. K.
    Pal, Mahesh
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2008, 22 (04) : 233 - 242
  • [6] Potential of geographic information systems in building cost estimation and visualization
    Bansal, V. K.
    Pal, Mahesh
    [J]. AUTOMATION IN CONSTRUCTION, 2007, 16 (03) : 311 - 322
  • [7] Bansal Vijay K., 2009, Construction Innovation, V9, P406, DOI 10.1108/14714170910995949
  • [8] Construction schedule review in GIS with a navigable 3D animation of project activities
    Bansal, V. K.
    Pal, Mahesh
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (05) : 532 - 542
  • [9] BANSAL VK, 1916, P WORLD AC SCI ENG T, V26, P307
  • [10] An algorithm for the implementation of safety improvement programs
    Cagno, E
    Di Giulio, A
    Trucco, P
    [J]. SAFETY SCIENCE, 2001, 37 (01) : 59 - 75