THE EFFECTS OF DELAYS IN ALGERIAN CONSTRUCTION PROJECTS: AN EMPIRICAL STUDY

被引:4
|
作者
Salhi, Roumeissa [1 ]
Messaoudi, Karima [1 ]
机构
[1] Univ 20 Aout 1955, Dept Civil Engn, LMGHU Lab, BP 26,El Hadaiek St, Skikda 21000, Algeria
关键词
construction management; construction delay; effects of delay; time control; Algeria; SMART-PLS;
D O I
10.2478/ceer-2021-0027
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper examines the effects of delays in the Algerian construction industry in order to identify the various critical aspects of the causes for improving the economy in the construction sector. A questionnaire survey was conducted to assess the perceptions of all players in the construction industry, which led to the identification of the most significant impacts of delays. The results show that ten main effects of delays in the construction sector are at the origin of many constraints that have a negative impact on the economy of the country. Further, the factor analysis technique was performed to categorize the identified effects into main groups, and it yielded 5 groups (factors). As an important contribution, the relationship between these groups was tested using the SMART-PLS, and a structural model has been developed. Also, a comparative study with other previous works on the most critical effect of delays in construction projects has been conducted and the results show that the main effects of delays in the construction industry are at the root of many constraints in reaching and achieving the objectives.
引用
收藏
页码:218 / 254
页数:37
相关论文
共 50 条
  • [21] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS.
    Kraiem, Zaki M.
    Diekmann, James E.
    Journal of Construction Engineering and Management, 1987, 113 (04) : 591 - 602
  • [22] Emperical Study of Critical Risk Factors Causing Delays in Construction Projects
    Khan, Rao Aamir
    Gul, Warda
    PROCEEDINGS OF THE 2017 9TH IEEE INTERNATIONAL CONFERENCE ON INTELLIGENT DATA ACQUISITION AND ADVANCED COMPUTING SYSTEMS: TECHNOLOGY AND APPLICATIONS (IDAACS), VOL 2, 2017, : 900 - 906
  • [23] AN EMPIRICAL STUDY ON THE PROBLEMS OF RUNNING DESIGN AND BUILD PROJECTS IN CONSTRUCTION
    Lam, Edmond W. M.
    Chan, Albert P. C.
    Chan, Daniel W. M.
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2007, 7 (01) : 1 - 15
  • [24] An Empirical Study on the Generation Mechanism of NIMBY Conflicts of Construction Projects
    Guang-she Jia
    Song-yu Yan
    Wen-jun Wang
    Ralf Müller
    Chen Lin
    Frontiers of Engineering Management, 2016, (01) : 39 - 49
  • [25] An Empirical Study on Flexibility: A Critical Success Factor of Construction Projects
    Rashmi Shahu
    Ashok K. Pundir
    L. Ganapathy
    Global Journal of Flexible Systems Management, 2012, 13 (3) : 123 - 128
  • [26] Empirical Study on the Obstacles to the Success of Joint Ventures in Construction Projects
    Lu, Chen
    Yu, Zhiwei
    Wang, Xuetong
    Hong, Yuming
    ADVANCES IN CIVIL ENGINEERING, 2020, 2020
  • [27] An Empirical Study on the Generation Mechanism of NIMBY Conflicts of Construction Projects
    Guangshe Jia
    Songyu Yan
    Wenjun Wang
    Ralf Mller
    Chen Lin
    Frontiers of Engineering Management, 2016, 3 (01) : 39 - 49
  • [28] An Empirical Study on the Generation Mechanism of NIMBY Conflicts of Construction Projects
    Jia, Guang-she
    Yan, Song-yu
    Wang, Wen-jun
    Mueller, Ralf
    Lin, Chen
    FRONTIERS OF ENGINEERING MANAGEMENT, 2016, 3 (01) : 39 - 49
  • [29] Causes of delays on construction projects: a comprehensive list
    Durdyev, Serdar
    Hosseini, M. Reza
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2019, 13 (01) : 20 - 46
  • [30] Causes of Construction Projects Delays: A qualitative analysis
    Rudeli, N.
    Viles, E.
    Gonzalez, J.
    Santilli, A.
    MEMORIA INVESTIGACIONES EN INGENIERIA, 2018, (16): : 71 - 84