THE EFFECTS OF DELAYS IN ALGERIAN CONSTRUCTION PROJECTS: AN EMPIRICAL STUDY

被引:4
|
作者
Salhi, Roumeissa [1 ]
Messaoudi, Karima [1 ]
机构
[1] Univ 20 Aout 1955, Dept Civil Engn, LMGHU Lab, BP 26,El Hadaiek St, Skikda 21000, Algeria
关键词
construction management; construction delay; effects of delay; time control; Algeria; SMART-PLS;
D O I
10.2478/ceer-2021-0027
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper examines the effects of delays in the Algerian construction industry in order to identify the various critical aspects of the causes for improving the economy in the construction sector. A questionnaire survey was conducted to assess the perceptions of all players in the construction industry, which led to the identification of the most significant impacts of delays. The results show that ten main effects of delays in the construction sector are at the origin of many constraints that have a negative impact on the economy of the country. Further, the factor analysis technique was performed to categorize the identified effects into main groups, and it yielded 5 groups (factors). As an important contribution, the relationship between these groups was tested using the SMART-PLS, and a structural model has been developed. Also, a comparative study with other previous works on the most critical effect of delays in construction projects has been conducted and the results show that the main effects of delays in the construction industry are at the root of many constraints in reaching and achieving the objectives.
引用
收藏
页码:218 / 254
页数:37
相关论文
共 50 条
  • [1] Underlying causes and mitigation measures of delays in construction projects An empirical study
    Arantes, Amilcar
    Ferreira, Luis Miguel D. F.
    JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2020, 25 (02) : 165 - 181
  • [2] Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso
    Bagaya, Ousseni
    Song, Jinbo
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (05)
  • [3] THE EFFECTS OF DELAYS IN ROAD CONSTRUCTION PROJECTS IN TRIPOLI, LIBYA
    Alfakhri, Aboubaker. Y. Y.
    Ismail, Amiruddin
    Khoiry, Muhamad Azry
    INTERNATIONAL JOURNAL OF TECHNOLOGY, 2018, 9 (04) : 766 - 774
  • [4] Empirical Study to Determine Fragmentation of Construction Projects
    Alashwal, Ali Mohammed
    Fong, Patrick Sik-Wah
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (07)
  • [5] An empirical study on stakeholder management in construction projects
    Srinivasan, N. P.
    Dhivya, S.
    MATERIALS TODAY-PROCEEDINGS, 2020, 21 : 60 - 62
  • [6] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS
    KRAIEM, ZM
    DIEKMANN, JE
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1987, 113 (04): : 591 - 602
  • [7] Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects
    San Santoso, Djoen
    Soeng, Sothy
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (06)
  • [8] Study the delays and conflicts for construction projects and their mutual relationship: A review
    Tariq, Junaid
    Gardezi, S. Shujaa Safdar
    AIN SHAMS ENGINEERING JOURNAL, 2023, 14 (01)
  • [9] Empirical Study upon Management Collaboration in Construction Projects
    Zhen, Zhilu
    Jian, Jianru
    Zhang, Yanbin
    CIVIL ENGINEERING, ARCHITECTURE AND SUSTAINABLE INFRASTRUCTURE II, PTS 1 AND 2, 2013, 438-439 : 1647 - +
  • [10] Evaluating Social Performance of Construction Projects: An Empirical Study
    Xiahou, Xiaer
    Tang, Yuchun
    Yuan, Jingfeng
    Chang, Tengyuan
    Liu, Ping
    Li, Qiming
    SUSTAINABILITY, 2018, 10 (07)