摘要
In this paper the resource-constrained project scheduling problem with multiple execution modes for each activity and the makespan as the minimization criterion is considered. A simulated annealing approach to solve this problem is presented. The feasible solution representation is based on a precedence feasible list of activities and a mode assignment. A comprehensive computational experiment is described, performed on a set of standard test problems constructed by the ProGen project generator. The results are analyzed and discussed and some final remarks are included.
引用
收藏
页码:137 / 155
页数:19
相关论文
共 40 条
[1]  
Aarts E., 1997, LOCAL SEARCH COMBINA, P91, DOI DOI 10.1038/S41598-021-83315-9
[2]   SCHEDULING SUBJECT TO RESOURCE CONSTRAINTS - CLASSIFICATION AND COMPLEXITY [J].
BLAZEWICZ, J ;
LENSTRA, JK ;
KAN, AHGR .
DISCRETE APPLIED MATHEMATICS, 1983, 5 (01) :11-24
[3]   Resource-constrained project scheduling by simulated annealing [J].
Boctor, FF .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1996, 34 (08) :2335-2351
[4]   A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes [J].
Boctor, FF .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 90 (02) :349-361
[5]   HEURISTICS FOR SCHEDULING PROJECTS WITH RESOURCE RESTRICTIONS AND SEVERAL RESOURCE-DURATION MODES [J].
BOCTOR, FF .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1993, 31 (11) :2547-2558
[6]  
BOULEIMEN K, 1998, P 6 INT WORKSH PROJ, P19
[7]   A branch and bound algorithm for the resource-constrained project scheduling problem [J].
Brucker, P ;
Knust, S ;
Schoo, A ;
Thiele, O .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1998, 107 (02) :272-288
[9]   A simulated annealing algorithm for resource constrained project scheduling problems [J].
Cho, JH ;
Kim, YD .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1997, 48 (07) :736-744
[10]   A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM [J].
DEMEULEMEESTER, E ;
HERROELEN, W .
MANAGEMENT SCIENCE, 1992, 38 (12) :1803-1818