Failure analysis of cracked 2.25Cr-1.0Mo steel tubes of an oil refinery boiler

被引:12
作者
Ahmadi, Azin [1 ]
Akmal, Mohmad Shayegani [1 ]
Pasha, Amir [1 ]
Yareie, Shahram [1 ]
机构
[1] RIPI, Corros Res Grp, Tehran, Iran
关键词
Failure analysis; 2.25Cr-1.0Mo steel; Stress corrosion cracking; Boiler tube; Finite element analysis; STRESS-CORROSION CRACKING; SUPER-HEATER TUBES; LINE;
D O I
10.1016/j.engfailanal.2020.104435
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
After failure of a refinery boiler, some cracks were detected in its tubes made of 2.25Cr-1Mo steel. The tubes were in the boiler superheater section. To determine causes of the cracking, samples were taken from the tubes, and different microscopical and analytical techniques such as scanning electron microscopy (SEM) and mechanical tests were used. Furthermore, finite element analysis (FEA) was used to evaluate the stress conditions in one of the cracked tubes. The results of analysis showed that the tube material was in accordance with the ASTM A213 chemical composition requirement however based on the calculated J-factor, the material was susceptible to temper embrittlement. The FEA results showed tensile residual stress formed at welding zone due to non-alignment before tubes welding. Considering the intergranular propagation of the cracks, the hardness of HAZ and other findings, it was concluded that stress corrosion cracking was the major damage mechanism.
引用
收藏
页数:10
相关论文
共 28 条
[1]   Failure investigation of secondary super-heater tubes in a power boiler [J].
Abou-elazm, A. Saad ;
El Mahallawi, I. ;
Abdel-karim, R. ;
Rashad, R. .
ENGINEERING FAILURE ANALYSIS, 2009, 16 (01) :433-448
[2]   Thermal fatigue and corrosion fatigue in heat recovery area wall side tubes [J].
Ahmad, J. ;
Purbolaksono, J. ;
Beng, L. C. .
ENGINEERING FAILURE ANALYSIS, 2010, 17 (01) :334-343
[3]   Damage characterization in two reformer heater tubes after nearly 10 years of service at different operative and maintenance conditions [J].
Alvino, Antonello ;
Lega, Daniela ;
Giacobbe, Francesco ;
Mazzocchi, Vittorio ;
Rinaldi, Antonio .
ENGINEERING FAILURE ANALYSIS, 2010, 17 (7-8) :1526-1541
[4]  
[Anonymous], 2011, DAM MECH AFF FIX EQ
[5]  
[Anonymous], ASM INT HDB, P11
[6]  
[Anonymous], 2019, MAT FABR 2 1 4CR 1MO
[7]  
[Anonymous], 2015, ASME Code Section VIII
[8]  
[Anonymous], 2016, DES FABR OP EFF INSP
[9]  
ASTM, 2009, G1-03
[10]   Cracking of 2.25Cr-1.0Mo steel tube/stationary tube-sheet weldment of a heat-exchanger [J].
Azevedo, C. R. F. ;
Neto, F. Beneduce ;
Brandi, S. D. ;
Tschiptschin, A. P. .
ENGINEERING FAILURE ANALYSIS, 2008, 15 (06) :695-710