A case study on improving productivity in paint booth assembly

被引:1
|
作者
Jayakumar, P. [1 ]
Kumar, V. R. Sathish [1 ]
机构
[1] Amrita Vishwa Vidyapeetham, Dept Mech Engn, Amrita Sch Engn, Coimbatore, India
关键词
Cycle Time; Total Operating Cycle Time; Value Added activity; Non-Value-Added activity; Time study and Productivity; MANUFACTURING-INDUSTRY; IMPROVEMENT;
D O I
10.1016/j.matpr.2022.04.288
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Currently, all automotive industries are faced with the need to respond to rapidly changing customer needs, their desires and the fluctuations in the market demand. During the plant visit and subsequent discussion made with the production department and also according to the operation process chart put up in the process study, it was noticed that the efficient time involved in the sub assembly process is less. Hence, this project work is conducted live to study the existing cycle time of a single model sub assembly line and suggesting improved methods to reduce the non-value-added activities, thereby reducing the cycle time in order to improve the efficiency of the sub assembly line and increase overall productivity. This case study is conducted in a leading garage equipment manufacturing industry in south India, which engages in manufacturing, designing and servicing garage equipment's. Currently, this plant is manufacturing 25 paint booths (1.4 paint booth assembly per shift) which the company foresees a growth in demand for paint booth assembly and gearing to scale up its production rate to 40 paint booths (2.5 paint booth assembly in a shift) including Sub assembly 6 which has been newly added in the paint booth assembly to meet out its monthly requirement and achieved.Copyright (c) 2022 Elsevier Ltd. All rights reserved. Selection and peer-review under responsibility of the scientific committee of the Second International Conference on Engineering Materials, Metallurgy and Manufacturing.
引用
收藏
页码:1054 / 1059
页数:6
相关论文
共 50 条
  • [41] OIL-WASH PAINT SPRAY BOOTH MINIMIZES MAINTENANCE
    不详
    INDUSTRIAL FINISHING, 1975, 51 (06): : 80 - 80
  • [42] Strategies for Improving Productivity through Digital Upgrades: Case Study on RPA Technology
    Bogoevici, Flavia
    PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON BUSINESS EXCELLENCE, 2024, 18 (01): : 3167 - 3184
  • [43] Improving productivity of automated tissue converting lines: an empirical model and a case study
    Cigolini, R
    Rossi, T
    PRODUCTION PLANNING & CONTROL, 2004, 15 (05) : 550 - 563
  • [44] Improving Productivity of the SMEs in Singapore - Case Studies
    Lee, A. J. L.
    Lim, R. Y. G.
    Ma, B.
    Xu, L. X. X.
    2013 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM 2013), 2013, : 73 - 77
  • [45] Improving productivity and efficiency of a vehicle seat assembly line in a manufacturing company
    Ismail, N
    Tai, SS
    Leman, Z
    2002 STUDENT CONFERENCE ON RESEARCH AND DEVELOPMENT, PROCEEDINGS: GLOBALIZING RESEARCH AND DEVELOPMENT IN ELECTRICAL AND ELECTRONICS ENGINEERING, 2002, : 94 - 97
  • [46] Paint booth waste as an alternative aggregate for the production of interlocking concrete blocks
    Catarina Monteiro Câmara
    Suéllen Tonatto Ferrazzo
    William Mateus Kubiaki Levandoski
    Cristina Vitorino da Silva
    Eduardo Pavan Korf
    Scientific Reports, 14
  • [47] Human-Robot Interaction for Improving Fuselage Assembly Tasks: A Case Study
    Laudante, Elena
    Greco, Alessandro
    Caterino, Mario
    Fera, Marcello
    APPLIED SCIENCES-BASEL, 2020, 10 (17):
  • [48] Treatment of paint spray booth off-gases in a fungal biofilter
    Qi, B
    Moe, WM
    Kinney, KA
    JOURNAL OF ENVIRONMENTAL ENGINEERING-ASCE, 2005, 131 (02): : 180 - 189
  • [49] Paint booth waste as an alternative aggregate for the production of interlocking concrete blocks
    Camara, Catarina Monteiro
    Ferrazzo, Suellen Tonatto
    Levandoski, William Mateus Kubiaki
    da Silva, Cristina Vitorino
    Korf, Eduardo Pavan
    SCIENTIFIC REPORTS, 2024, 14 (01)
  • [50] PAINT BOOTH VOC EMISSION REDUCTION THROUGH AIR RECIRCULATION.
    Bhushan, Dinesh
    Metal Finishing, 1988, 86 (05) : 51 - 55