Mean-conditional value at risk model for the stochastic project scheduling problem

被引:32
作者
Rezaei, Fatemeh [1 ]
Najafi, Amir Abbas [1 ]
Ramezanian, Reza [1 ]
机构
[1] KN Toosi Univ Technol, Fac Ind Engn, Tehran, Iran
关键词
Stochastic project scheduling; Conditional-value-at risk; Scheduling policy; NET PRESENT VALUE; DAMPING OPTIMIZATION ALGORITHM; ACTIVITY DURATION; CASH FLOWS; NSGA-II; AT-RISK; MANAGEMENT; NETWORKS; MAXIMIZE;
D O I
10.1016/j.cie.2020.106356
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Every project faces different opportunities and risks during its lifecycle. Risks are the factors that can disrupt the successful implementation of projects and cause failure in achieving project goals. Advancing the project while considering its risks is one of the most essential aspects of project management. Planning and scheduling can be applied in a way that reduces the risks in the management of projects. In this paper, a new scenario-based mean-conditional value-at-risk (CVaR) model is developed to minimize the risk of the project's net present value (NPV). Moreover, the trade-off between expected NPV and the risk of NPV is considered in this study. Start time policies are also used to specify the start times of project activities. Two multi-objective optimization algorithms including Non-dominated Sorting Genetic Algorithms (NSGA-II), and Multi-Objective Vibration Damping Optimization (MOVDO) are applied to identify the Pareto optimal solution. The efficiency of the algorithms is assessed based on some performance criteria. The results of the computational experiments show that at identical run time MOVDO functions better in terms of hypervolume indicator, while NSGA- II better results in other performance metrics.
引用
收藏
页数:16
相关论文
共 53 条
[1]  
[Anonymous], 2007, EVOLUTIONARY ALGORIT
[2]  
[Anonymous], 2009, P 2 INT C IR OP RES
[3]  
[Anonymous], 2001, Multi-Objective Optimization Using Evolutionary Algorithms
[4]  
[Anonymous], 2017, PROJ MAN BOD KNOWL, V6
[5]   New competitive results for the stochastic resource-constrained project scheduling problem: exploring the benefits of pre-processing [J].
Ashtiani, Behzad ;
Leus, Roel ;
Aryanezhad, Mir-Bahador .
JOURNAL OF SCHEDULING, 2011, 14 (02) :157-171
[7]   On using the hypervolume indicator to compare Pareto fronts: Applications to multi-criteria optimal experimental design [J].
Cao, Yongtao ;
Smucker, Byran J. ;
Robinson, Timothy J. .
JOURNAL OF STATISTICAL PLANNING AND INFERENCE, 2015, 160 :60-74
[8]   Engineering and contracting projects: A value at risk based approach to portfolio balancing [J].
Caron, Franco ;
Fumagalli, Mauro ;
Rigamonti, Alvaro .
International Journal of Project Management, 2007, 25 (06) :569-578
[9]   Moments and distribution of the net present value of a serial project [J].
Creemers, Stefan .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 267 (03) :835-848
[10]   Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure [J].
Creemers, Stefan .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 267 (01) :16-22