A case study in a two-stage hybrid flow shop with setup time and dedicated machines

被引:127
作者
Lin, HT
Liao, CJ
机构
[1] Natl Taiwan Univ, Dept Ind Management, Taipei 106, Taiwan
[2] Natl Chin Yi Inst Technol, Dept Ind Engn & Management, Chungli, Taiwan
关键词
two-stage hybrid flow shop; sequence-dependent setup time; dedicated machine; weighted maximal tardiness;
D O I
10.1016/S0925-5273(03)00011-2
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In this paper we address a scheduling problem taken from a label sticker manufacturing company. The production system is a two-stage hybrid flow shop with the characteristics of sequence-dependent setup time at stage 1, dedicated machines at stage 2, and two due dates. The objective is to schedule one day's mix of label stickers through the shop such that the weighted maximal tardiness is minimized. A heuristic is proposed to find the near-optimal schedule for the problem. The performance of the heuristic is evaluated by comparing its solution with both the optimal solution for small-sized problems and the solution obtained by the scheduling method currently used in the shop. As the heuristic is beneficial to the company, it will be implemented in the near future. (C) 2003 Elsevier Science B.V. All rights reserved.
引用
收藏
页码:133 / 143
页数:11
相关论文
共 28 条
[1]   BRANCH AND BOUND ALGORITHM FOR THE FLOW-SHOP WITH MULTIPLE PROCESSORS [J].
BRAH, SA ;
HUNSUCKER, JL .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1991, 51 (01) :88-99
[2]   MINMAX EARLINESS TARDINESS SCHEDULING IN IDENTICAL PARALLEL MACHINE SYSTEM USING GENETIC ALGORITHMS [J].
CHENG, RW ;
GEN, MS ;
TOZAWA, T .
COMPUTERS & INDUSTRIAL ENGINEERING, 1995, 29 :513-517
[3]   A STATE-OF-THE-ART REVIEW OF PARALLEL-MACHINE SCHEDULING RESEARCH [J].
CHENG, TCE ;
SIN, CCS .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1990, 47 (03) :271-292
[4]   Complexity of parallel machine scheduling with processing-plus-wait due dates to minimize maximum absolute lateness [J].
Cheng, TCE ;
Kovalyov, MY .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 114 (02) :403-410
[5]  
Deal D. E., 1991, Journal of Information & Optimization Sciences, V12, P407
[6]   HEURISTICS FOR SCHEDULING FLEXIBLE FLOW LINES [J].
DING, FY ;
KITTICHARTPHAYAK, D .
COMPUTERS & INDUSTRIAL ENGINEERING, 1994, 26 (01) :27-34
[7]  
Glover F., 1977, DECISION SCI, V8, P156, DOI DOI 10.1111/J.1540-5915.1977.TB01074.X
[8]   SCHEDULES FOR A 2-STAGE HYBRID FLOWSHOP WITH PARALLEL MACHINES AT THE 2ND STAGE [J].
GUPTA, JND ;
TUNC, EA .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1991, 29 (07) :1489-1502
[9]   2-STAGE, HYBRID FLOWSHOP SCHEDULING PROBLEM [J].
GUPTA, JND .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1988, 39 (04) :359-364
[10]   THE 2-MACHINE SEQUENCE DEPENDENT FLOWSHOP SCHEDULING PROBLEM [J].
GUPTA, JND ;
DARROW, WP .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1986, 24 (03) :439-446