A bi-objective truck scheduling problem in a cross-docking center with probability of breakdown for trucks

被引:47
作者
Amini, Alireza
Tavakkoli-Moghaddam, Reza [1 ]
机构
[1] Univ Tehran, Sch Ind Engn, Tehran, Iran
关键词
Cross docking; Truck scheduling; Multi-objective optimization; Breakdown; Response surface methodology; Meta-heuristics; DIFFERENTIAL EVOLUTION; OPTIMIZATION; HEURISTICS; ALGORITHMS; MAKESPAN;
D O I
10.1016/j.cie.2016.03.023
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
This paper addresses a truck scheduling problem in a cross-docking center, in which trucks may confront breakdowns during their service times. In fact, the number of breakdowns in one unit of time for each truck follows a Poisson distribution function. On the other hand, customers are promised to receive required items in a pre-determined time; so, a due date is assigned to each outbound truck. Thus, a bi-objective linear mathematical model is developed inspired by models in the body of the respective literature. A complete enumeration method is employed to find optimum solutions subject to the complexity of large-scale problems, and we modify three multi-objective meta-heuristics; namely, Non-dominated Sorting Genetic Algorithm II (NSGA-II), Multi-Objective Simulated Annealing (MOSA) and Multi-Objective Differential Evolutionary (MODE). In addition, a Response Surface Methodology (RSM) as a statistical tool is used to find an appropriate amount of factors associated with the forgoing meta-heuristics. Finally, the performances of the proposed meta-heuristics are measured and compared with each other. (C) 2016 Elsevier Ltd. All rights reserved.
引用
收藏
页码:180 / 191
页数:12
相关论文
共 37 条
[1]   A bounded dynamic programming approach to schedule operations in a cross docking platform [J].
Alpan, Guelguen ;
Larbi, Rim ;
Penz, Bernard .
COMPUTERS & INDUSTRIAL ENGINEERING, 2011, 60 (03) :385-396
[2]  
Apte U.M., 2000, International Journal of Logistics Research and Applications, V3, P291, DOI [10.1080/713682769, DOI 10.1080/713682769]
[3]   Multi-objective genetic-based algorithms for a cross-docking scheduling problem [J].
Arabani, A. Boloori ;
Zandieh, M. ;
Ghomi, S. M. T. Fatemi .
APPLIED SOFT COMPUTING, 2011, 11 (08) :4954-4970
[4]   Meta-heuristics implementation for scheduling of trucks in a cross-docking system with temporary storage [J].
Arabani, A. R. Boloori ;
Ghomi, S. M. T. Fatemi ;
Zandieh, M. .
EXPERT SYSTEMS WITH APPLICATIONS, 2011, 38 (03) :1964-1979
[5]   A multi-criteria cross-docking scheduling with just-in-time approach [J].
Arabani, A. R. Boloori ;
Ghomi, S. M. T. Fatemi ;
Zandieh, M. .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 49 (5-8) :741-756
[6]   Cross dock scheduling: Classification, literature review and research agenda [J].
Boysen, Nils ;
Fliedner, Malte .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2010, 38 (06) :413-422
[7]   Scheduling inbound and outbound trucks at cross docking terminals [J].
Boysen, Nils ;
Fliedner, Malte ;
Scholl, Armin .
OR SPECTRUM, 2010, 32 (01) :135-161
[8]   Truck scheduling at zero-inventory cross docking terminals [J].
Boysen, Nils .
COMPUTERS & OPERATIONS RESEARCH, 2010, 37 (01) :32-41
[9]   Minimizing makespan in two-stage hybrid cross docking scheduling problem [J].
Chen, Feng ;
Song, Kailei .
COMPUTERS & OPERATIONS RESEARCH, 2009, 36 (06) :2066-2073
[10]   Minimizing the makespan in a two-machine cross-docking flow shop problem [J].
Chen, Feng ;
Lee, Chung-Yee .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2009, 193 (01) :59-72