Economic assessment of novel amine based CO2 capture technologies integrated in power plants based on European Benchmarking Task Force methodology

被引:95
作者
Manzolini, G. [1 ]
Fernandez, E. Sanchez [2 ]
Rezvani, S. [3 ]
Macchi, E. [1 ]
Goetheer, E. L. V. [2 ]
Vlugt, T. J. H. [4 ]
机构
[1] Politecn Milan, I-20156 Milan, Italy
[2] TNO Gas Treatment, NL-2628 CA Delft, Netherlands
[3] Univ Ulster, Belfast BT15 1ED, Antrim, North Ireland
[4] Delft Univ Technol, NL-2628 CB Delft, Netherlands
关键词
CESAR-1; solvent; 2-Amino-2-methyl-propanol; Piperazine; MEA; Post-combustion CO2 capture (PCC); Economic analysis; PILOT-PLANT; AQUEOUS MEA; FLUE-GAS; DEGRADATION; PERFORMANCE; MONOETHANOLAMINE; EMISSIONS; SOLVENTS; SCALE; COST;
D O I
10.1016/j.apenergy.2014.04.066
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
The objective of this paper is to assess the economic advantages of an innovative solvent for CO2 capture on state-of-the-art solvents. The CESAR-1 solvent, which is an aqueous solution of 2-amino-2-methylpropanol (AMP) and piperazine (PZ), is applied both to advanced supercritical pulverised (ASC) coal and natural gas combined cycle (NGCC) power plants with post-combustion CO2 capture units. The methodology includes process model developments using commercial simulation programs, which determine the thermodynamic properties of the selected power plants and the performance of the CO2 capture units. The results show that the techno-economic benefit of CESAR-1 versus MEA is more significant for ASC than that for NGCC due to a higher concentration of CO2 in the flue gas. This follows from the fact that the switch from MEA to CESAR-1 solvents reduces the electricity cost by 4.16 (sic)/MW h in the case of the ASC plant compared to 0.67 (sic)/MW h in connection with the proposed NGCC plant. Based on the above figures, we can conclude that CESAR-1 reduces the cost of CO2 avoided compared to MEA by 6 (sic)/t CO2 and 2 (sic)/t CO2 for the selected ASC and NGCC plants respectively. In view of that, the techno-economics can be improved if the CO2 capture plant is designed to operate using the CESAR-1 absorption technology due to a reduction in the regeneration energy and the solvent recirculation rate (considering its higher CO2 net capacity). However, the variable costs of running the capture plant are higher for the CESAR-1 solvent due to the higher cost of the amines. (C) 2014 Published by Elsevier Ltd.
引用
收藏
页码:546 / 558
页数:13
相关论文
共 70 条
  • [1] AACE, 2003, COND TECHN EC EV APP
  • [2] CO2 capture from power plants -: Part II.: A parametric study of the economical performance based on mono-ethanolamine
    Abu-Zahra, Mohammad R. M.
    Niederer, John P. M.
    Feron, Paul H. M.
    Versteeg, Geert F.
    [J]. INTERNATIONAL JOURNAL OF GREENHOUSE GAS CONTROL, 2007, 1 (02) : 135 - 142
  • [3] [Anonymous], THE FUT OF COAL
  • [4] [Anonymous], 2002, UPD COST PERF EST FO
  • [5] [Anonymous], 2009, BIOMASS CCS STUDY
  • [6] [Anonymous], 2010, Cost and Performance Baseline for Fossil Energy Plants, Volume 1: Bituminous Coal and Natural Gas to Electricity, V1
  • [7] Integration of CO2 capture unit using single- and blended-amines into supercritical coal-fired power plants:: Implications for emission and energy management
    Aroonwilas, Adisorn
    Veawab, Amornuadee
    [J]. INTERNATIONAL JOURNAL OF GREENHOUSE GAS CONTROL, 2007, 1 (02) : 143 - 150
  • [8] Performance of MEA and amine-blends in the CSIRO PCC pilot plant at Loy Yang Power in Australia
    Artanto, Yuli
    Jansen, James
    Pearson, Pauline
    Thong Do
    Cottrell, Aaron
    Meuleman, Erik
    Feron, Paul
    [J]. FUEL, 2012, 101 : 264 - 275
  • [9] Bergsma EJ, 2011, AMP EMISSIONS PILOT
  • [10] Bhattacharyya SC, 2011, ENERGY ECONOMICS: CONCEPTS, ISSUES, MARKETS AND GOVERNANCE, P1, DOI 10.1007/978-0-85729-268-1