Optimal participation and risk mitigation of wind generators in an electricity market

被引:98
作者
Dukpa, A. [1 ]
Duggal, I. [2 ]
Venkatesh, B. [2 ]
Chang, L. [1 ]
机构
[1] Univ New Brunswick, Dept Elect & Comp Engn, Fredericton, NB E3B 5A3, Canada
[2] Ryerson Univ, Dept Elect & Comp Engn, Toronto, ON, Canada
关键词
UNIT COMMITMENT; POWER; OPTIMIZATION; MINIMIZATION; STORAGE; ENERGY;
D O I
10.1049/iet-rpg.2009.0016
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Forecasted output of wind electric generators (WEGs) in a 24-h horizon has large uncertainties. These uncertainties pose a challenge while computing optimal bids necessary for participating in the day-ahead unit commitment process (DACP) thus limiting their integration and success. This study proposes a new optimal participation strategy for a WEG that employs an energy storage device (ESD) for participating in the DACP. The WEG is modelled to function as a price-taker. The proposed formulation has two objectives: (a) maximise returns from the market considering the best forecast; and (b) minimise risks considering the forecast uncertainties. Risk in the participation strategy is quantified by computing expected energy not served (EENS). The multiobjective mixed integer linear programming formulation is transformed into a fuzzy optimisation problem and solved. Through suitable examples, the ESD is shown to play two important roles: (a) it helps to shift wind energy produced during hours with low marginal prices to those hours with higher marginal prices by appropriately storing and releasing it. This shift can be forward or backward in time. (b) The second crucial role played by ESD, upon minimising EENS, is to maintain an energy reserve akin to spinning reserve such that the risk of the optimal participation schedule is the least.
引用
收藏
页码:165 / 175
页数:11
相关论文
共 19 条
  • [1] ABBEY C, 2005, IEEE 36 POW EL SPEC
  • [2] *AWS TRUEW LLC, AN IMP LARG WIND GEN
  • [3] Trading wind generation in short term energy markets
    Bathurst, GN
    Weatherill, J
    Strbac, G
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2002, 17 (03) : 782 - 789
  • [4] On the optimization of the daily operation of a wind-hydro power plant
    Castronuovo, ED
    Lopes, JAP
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2004, 19 (03) : 1599 - 1606
  • [5] Assessment of the cost associated with wind generation prediction errors in a liberalized electricity market
    Fabbri, A
    Gómez, T
    Román, S
    Abbad, JR
    Quezada, VHM
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2005, 20 (03) : 1440 - 1446
  • [6] Stochastic joint optimization of wind generation and pumped-storage units in an electricity market
    Garcia-Gonzalez, Javier
    Ruiz de la Muela, Rocio Moraga
    Matres Santos, Luz
    Mateo Gonzalez, Alicia
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2008, 23 (02) : 460 - 468
  • [7] Optimal electricity market for wind power
    Holttinen, H
    [J]. ENERGY POLICY, 2005, 33 (16) : 2052 - 2063
  • [8] KAMIBAYASHI M, 2002, IEEE PES WINT 2001 C
  • [9] LANG Y, 2007, IEEE CAN REV GREEN P, V56, P10
  • [10] MARTI I, 2006, EWEC 2006 ATH