A feasibility study of industrial wastewater recovery using electrodialysis reversal

被引:73
作者
Chao, Yu-Mei [2 ]
Liang, T. M. [1 ]
机构
[1] Ind Technol Res Inst, Energy & Environm Res Labs, Hsinchu 310, Taiwan
[2] China Steel Corp, New Mat R&D Dept, Chem Proc & Water Treatment Sect, Kaohsiung 81233, Taiwan
关键词
electrodialysis reversal; wastewater reclamation; reuse;
D O I
10.1016/j.desal.2007.04.065
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
A wastewater reclamation and reuse "mini-plant" was established at the site of China Steel Corporation (CSC) wastewater treatment plant. The purpose of the mini-plant is to demonstrate the technical and economical feasibility of electrodialysis reversal (EDR) process. The mini-plant includes a sand filtration unit and an EDR unit which has a daily treatment capacity of 350 CMD. Raw wastewater had an averaged conductivity of 3860 mu S/cm, pH between 7.7 and 8.3, and COD between 30 and 70 mg/L. When the EDR unit operates at a 75% of water reclamation rate, 92% of desalination rate, 98% of chlorine ion removal, 80% of sulfate removal, 99% of calcium ion removal, and 51% of COD removal rate can be achieved. The water quality of product stream is 305 mu S/cm for conductivity, 13 mg/L for chlorine ion, 86 mg/L for sulfate, 1.4 mg/L for calcium ion, and of 20 mg/L for COD concentration. Operation cost of the EDR mini-plant was also estimated in this project. The electricity required for electrodes power supply and pumping is 0.85 kW h per cubic meter of treated water. Total operation cost including electricity fee and chemical cost is about $0.146 per cubic meter of treated water.
引用
收藏
页码:433 / 439
页数:7
相关论文
共 8 条
[1]  
Chao Y. -M., 2005, ESTABLISHMENT APPL W
[2]  
Chao Y. -M., 2005, FEASIBILITY TEST WAS
[3]  
Chao Y. -M., 2005, PURIFICATION PROCESS
[4]  
CHOU SS, 2001, DEV RINSING WATER RE
[5]  
LIANG TM, 2004, IWA SPEC C WAT ENV M
[6]  
LIANG TM, 2004, IWA WAT WORLD C MARR
[7]  
LIANG TM, 2003, C EFFL COND CONTR CT
[8]  
LIANG TM, 2003, 8 C WAT REUS RECL TE