Integrated BIM-based simulation for automated time-space conflict management in construction projects

被引:33
作者
Dashti, Mohammad Saleh [1 ]
RezaZadeh, Mohammad [1 ]
Khanzadi, Mostafa [1 ]
Taghaddos, Hosein [2 ]
机构
[1] Iran Univ Sci & Technol, Sch Civil Engn, POB 16846-13114, Tehran, Iran
[2] Univ Tehran, Sch Civil Engn, Coll Engn, POB 14395-477, Tehran, Iran
关键词
Time-space planning; Scheduling; Motion planning; Discrete Event Simulation (DES); Optimization; Building Information Modeling (BIM); Rapidly-exploring Random Tree (RRT)  algorithm; WORK SPACE; SYSTEM; QUANTIFICATION; CONGESTION; RESOLUTION;
D O I
10.1016/j.autcon.2021.103957
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The time-space conflicts may have severe negative impacts on the productivity and safety level in a construction site. However, little attention is paid to propose an automated, integrated system for managing potential time space conflicts, considering the site space system's dynamic nature. This study contributes to the body of knowledge by proposing a novel integrated approach to manage time-space conflicts automatically. The proposed hybrid approach is based on Discrete Event Simulation (DES), Building Information Modeling (BIM), and Rapidly-exploring Random Tree (RRT) path planning. All types of time-space conflicts during the entire project timeline are automatically detected, evaluated, and resolved based on predefined if-then rules. The proposed approach is applied successfully in a real case study to estimate the project duration considering site space limitations. The results indicate that the proposed system can considerably prevent the negative impacts of time space conflicts, particularly in congested construction sites.
引用
收藏
页数:20
相关论文
共 71 条
[51]   Optimized Mobile Crane Path Planning in Discretized Polar Space [J].
Mousaei, Ali ;
Taghaddos, Hosein ;
Tak, Ala Nekouvaght ;
Behzadipour, Saeed ;
Hermann, Ulrich .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (05)
[52]   Strategic-operational construction management: Hybrid system dynamics and discrete event approach [J].
Pena-Mora, Feniosky ;
Han, Sangwon ;
Lee, SangHyun ;
Park, Moonseo .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2008, 134 (09) :701-710
[53]   Evaluating Mobile Crane Lift Operations Using an Interactive Virtual Reality System [J].
Pooladvand, Shiva ;
Taghaddos, Hosein ;
Eslami, Arash ;
Tak, Ala Nekouvaght ;
Hermann, Ulrich .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (11)
[54]  
Razavialavi S., 2013, P INT S AUT ROB CONS, P275
[55]   Strategy management of construction workspaces by conflict resolution algorithm and visualization model [J].
Rohani, Mohammad ;
Shafabakhsh, Gholamali ;
Haddad, Abdolhosein ;
Asnaashari, Ehsan .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2018, 25 (08) :1053-1074
[56]   Uncertainty-Aware Linear Schedule Optimization: A Space-Time Constraint-Satisfaction Approach [J].
Roofigari-Esfahan, Nazila ;
Razavi, Saiedeh .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2017, 143 (05)
[57]   Float Types in Construction Spatial Scheduling [J].
Said, Hisham M. M. ;
Lucko, Gunnar .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2016, 142 (12)
[58]  
Sariff N, 2006, IEEE ST CONF RES DEV, P182
[59]   Detection of spatio-temporal conflicts on a temporal 3D space system [J].
Song, YB ;
Chua, DKH .
ADVANCES IN ENGINEERING SOFTWARE, 2005, 36 (11-12) :814-826
[60]   Life Cycle Approach to Construction Workspace Modeling and Planning [J].
Su, Xing ;
Cai, Hubo .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (07)