Causes of delay to public infrastructure projects according to engineers representing different contract parties

被引:14
作者
Ahmad, Hesham S. [1 ]
Ayoush, Maha D. [2 ]
Al-Alwan, Majed S. [3 ]
机构
[1] Al Zaytoonah Univ Jordan, Dept Civil & Infrastruct Engn, Amman, Jordan
[2] Al Zaytoonah Univ Jordan, Dept Accounting, Amman, Jordan
[3] Jordanian Minist Publ Works & Housing, Amman, Jordan
关键词
Survey; Construction projects; Roads; Causes of delay; Contract parties; Public infrastructure; CONSTRUCTION PROJECTS; RESPONSE CATEGORIES; OPTIMAL NUMBER; ROAD;
D O I
10.1108/BEPAM-03-2019-0026
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Purpose The purpose of this paper is to investigate the main causes of delay in public construction projects. This is motivated by feedback from public construction experts concerning substantive delays during the last decade. The study thus seeks to help decision makers in Jordan and elsewhere identify problems and develop mitigating strategies. Design/methodology/approach Causes of delay were identified from previous related studies and then augmented after consultation with experts. This resulted in 56 delay factors classified into eight groups. The sampling frame for the study was defined in terms of public construction projects (mostly related to roads) owned by the Ministry of Public Works and Housing in Jordan. A survey was conducted with engineers working as representatives of the owner, contractors or consultants to elicit and evaluate the importance of the 56 delay factors. Findings Overall, 113 completed questionnaire responses were returned and analyzed to rank the causes of delay using the relative importance index method. Owners and consultants showed more interest in factors related to themselves, while contractors showed highest interest in an external factor related to the owner of services. Four recommendations are put forward for decision makers to mitigate against delays. Originality/value This research investigates a relatively large number of delay factors compared to other studies and these are categorized into groups to facilitate thematic understanding. Further, compared to previous related research, this research fills a gap by exploring the opinions of different contract parties.
引用
收藏
页码:153 / 179
页数:27
相关论文
共 38 条
[1]  
Abisuga A.O., 2014, J. Emerg. Trends Econ. Manag. Sci, V5, P371
[2]   Construction delays and their causative factors in Nigeria [J].
Aibinu, Ajibade Ayodeji ;
Odeyinka, Henry Agboola .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2006, 132 (07) :667-677
[3]  
Al-Tal S., 2017, SCI RES METHODS FUND
[4]  
[Anonymous], 2002, International Journal of Quality Reliability Management, V19, P551, DOI 10.1108/02656710210427520
[5]   Causes of delay in large construction projects [J].
Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia .
Int. J. Proj. Manage., 2006, 4 (349-357) :349-357
[6]  
Black T.R., 1999, Doing quantitative research in the social sciences: An integrated approach to research design, measurement, and statistics
[7]  
Cronbach LJ, 1951, PSYCHOMETRIKA, V16, P297
[8]   Causes of Delay in Building Construction Projects in Egypt [J].
El-Razek, M. E. Abd ;
Bassioni, H. A. ;
Mobarak, A. M. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2008, 134 (11) :831-841
[9]   Owners' perspective of factors contributing to project delay: case studies of road and bridge projects in Saudi Arabia [J].
Elawi, Ghazi Saad A. ;
Algahtany, Mohammed ;
Kashiwagi, Dean .
ICSDEC 2016 - INTEGRATING DATA SCIENCE, CONSTRUCTION AND SUSTAINABILITY, 2016, 145 :1402-1409
[10]  
Faleye B.A., 2008, Electronic Journal of Research in Educational Psychology, V16, P823