RESEARCH ON RESOURCE LEVELING PROBLEM UNDER RESOURCE CONSTRAINED CONDITION

被引:2
|
作者
Wang, Qiang [1 ]
Qi, Jian-Xun [1 ]
机构
[1] N China Elect Power Univ, Dept Business Management, Beijing 102206, Peoples R China
关键词
RCP scheduling problem; Resource leveling problem; Particle swarm optimization; Project management; Heuristic methods; Project scheduling; PROJECT; SEARCH;
D O I
10.1109/ICMLC.2009.5212393
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In this paper, a new problem is defined according to the actual project requirement. It is resource leveling problem under resource constrained condition. Unlike the single resource leveling problem, or the resource constrained scheduling problem, this new problem will consider not only resource usage evenness, but also the shortest project duration under resource constrained condition. A new objective function is designed and a particle swarm optimization (PSO) algorithm is presented to solve this problem.
引用
收藏
页码:901 / 906
页数:6
相关论文
共 50 条
  • [31] Resource-Constrained Project Scheduling Problem under Multiple Time Constraints
    Kong, Feng
    Dou, Dong
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (02)
  • [32] Resource Constrained Disassembly Line Balancing Problem
    Mete, Suleyman
    Cil, Zeynel Abidin
    Ozceylan, Eren
    Agpak, Kursad
    IFAC PAPERSONLINE, 2016, 49 (12): : 921 - 925
  • [33] Evolutionary algorithms for the resource constrained scheduling problem
    Frankola, Toni
    Golub, Marin
    Jakobovic, Domagoj
    PROCEEDINGS OF THE ITI 2008 30TH INTERNATIONAL CONFERENCE ON INFORMATION TECHNOLOGY INTERFACES, 2008, : 715 - 722
  • [34] Planning/scheduling methodology for the constrained resource problem
    1600, Morgan Kaufmann Publ Inc, San Mateo, CA, USA (02):
  • [35] A dynamic resource constrained project scheduling problem
    Villela da Silva, Andre Renato
    Ochi, Luiz Satoru
    INTERNATIONAL JOURNAL OF DATA MINING MODELLING AND MANAGEMENT, 2013, 5 (04) : 370 - 379
  • [36] A GRASP for a resource-constrained scheduling problem
    Sirdey R.
    Carlier J.
    Nace D.
    International Journal of Innovative Computing and Applications, 2010, 2 (03) : 143 - 149
  • [37] A DECOMPOSITION APPROACH FOR A RESOURCE CONSTRAINED SCHEDULING PROBLEM
    SERAFINI, P
    SPERANZA, MG
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1994, 75 (01) : 112 - 135
  • [38] A New Resource Constrained Project Scheduling Problem
    Liu, Xiaoxiang
    Jiang, Weigang
    Xie, Jianwen
    Jia, Yitian
    2009 ASIA-PACIFIC CONFERENCE ON INFORMATION PROCESSING (APCIP 2009), VOL 1, PROCEEDINGS, 2009, : 476 - +
  • [39] The Proactive Resource-Constrained Project Scheduling Problem with Resource Transfer Times
    Ma, Zhiqiang
    He, Zhengwen
    Wang, Nengmin
    PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 642 - 647
  • [40] Resource Constrained Multi-Project Scheduling Problem with Resource Transfer Times
    Suresh, M.
    Dutta, Pankaj
    Jain, Karuna
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2015, 32 (06)