Simulation-based scheduling for dynamic discrete manufacturing

被引:28
作者
Chong, CS [1 ]
Sivakumar, AI [1 ]
Gay, R [1 ]
机构
[1] Nanyang Technol Univ, Singapore Inst Mfg Technol, Singapore 638075, Singapore
来源
PROCEEDINGS OF THE 2003 WINTER SIMULATION CONFERENCE, VOLS 1 AND 2 | 2003年
关键词
D O I
10.1109/WSC.2003.1261590
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
A simulation-based real-time scheduling mechanism for dynamic discrete manufacturing is presented in this paper. Modified mean flow time performance for different scheduling approaches is compared through off-line simulation experiments, under dynamic manufacturing environments that are subjects to disturbances such as machine breakdowns. These experimental results are used as reference indices for the real-time scheduling mechanism to select the better scheduling approaches for further evaluation based on the actual manufacturing conditions. Discrete-event simulation is used on-line to evaluate the selected approaches and the corresponding schedules to determine the best solution. The selected schedule is used until the deviation of actual performance from the estimated one exceeds a given limit, or when a major event occurs. A new simulation is then performed with the remaining operations to select a new schedule.
引用
收藏
页码:1465 / 1473
页数:9
相关论文
共 30 条
[1]   Rescheduling job shops under random disruptions [J].
Abumaizar, RJ ;
Svestka, JA .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (07) :2065-2082
[2]   Match-up scheduling under a machine breakdown [J].
Akturk, MS ;
Gorgulu, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :81-97
[3]  
[Anonymous], P IEE WORKSH RESP MA
[4]  
Bongaerts L, 1998, IEEE INT CONF ROBOT, P2747, DOI 10.1109/ROBOT.1998.680761
[5]   Decomposition heuristics for robust job-shop scheduling [J].
Byeon, ES ;
Wu, SD ;
Storer, RH .
IEEE TRANSACTIONS ON ROBOTICS AND AUTOMATION, 1998, 14 (02) :303-313
[6]  
CHANG YL, 1985, ANN OPER RES, V3, P355
[7]   ANALYSIS OF PERIODIC AND EVENT-DRIVEN RESCHEDULING POLICIES IN DYNAMIC SHOPS [J].
CHURCH, LK ;
UZSOY, R .
INTERNATIONAL JOURNAL OF COMPUTER INTEGRATED MANUFACTURING, 1992, 5 (03) :153-163
[8]   REACTIVE SCHEDULING - IMPROVING THE ROBUSTNESS OF SCHEDULES AND RESTRICTING THE EFFECTS OF SHOP-FLOOR DISTURBANCES BY FUZZY-REASONING [J].
DORN, J ;
KERR, R ;
THALHAMMER, G .
INTERNATIONAL JOURNAL OF HUMAN-COMPUTER STUDIES, 1995, 42 (06) :687-704
[9]  
Holloway SW, 1997, ENGL LANG NOTES, V35, P1
[10]   Production scheduling/rescheduling in flexible manufacturing [J].
Jain, AK ;
Elmaraghy, HA .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (01) :281-309