Efficiency assessment of L-profiles and pipe fore-poling pre-support systems in difficult geological conditions: a case study

被引:3
作者
Elyasi, Ayub [1 ]
Moradi, Taher [2 ]
Moharrami, Javad [2 ]
Parnian, Saeid [2 ]
Mousazadeh, Akbar [3 ]
Nasseh, Sepideh [4 ]
机构
[1] Tarbiat Modares Univ, Dept Min Engn, Tehran, Iran
[2] Consultant Engn Inst Iman Sazan, Tehran, Iran
[3] Islamic Azad Univ, Dept Civil Engn, Naghadeh, Iran
[4] Ferdowsi Univ Mashhad, Dept Geol, Mashhad, Iran
关键词
sequential excavation method; alluvial material; numerical modeling; L-profiles; pipe fore-poling; monitoring; UMBRELLA ARCH; TUNNEL; REINFORCEMENT;
D O I
10.12989/sem.2016.57.6.1125
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Tunneling is one of the challenging tasks in civil engineering because it involves a variety of decision making and engineering judgment based on knowledge and experience. One of the challenges is to construct tunnels in risky areas under shallow overburden. In order to prevent the collapse of ceilings and walls of a large tunnels, in such conditions, either a sequential excavation method (SEM) or ground reinforcing method, or a combination of both, can be utilized. This research deals with the numerical modeling of L-profiles and pipe fore-poling pre-support systems in the adit tunnel in northwestern Iran. The first part of the adit tunnel has been drilled in alluvial material with very weak geotechnical parameters. Despite applying an SEM in constructing this tunnel, analyzing the results of numerical modeling done using FLAC3D, as well as observations during drilling, indicate the tunnel instability. To improve operational safety and to prevent collapse, pre-support systems, including pipe fore-poling and L-profiles were designed and implemented. The results of the numerical modeling coupled with monitoring during operation, as well as the results of instrumentation, indicate the efficacy of both these methods in tunnel collapse prevention. Moreover, the results of modeling using FLAC3D and SECTION BUILDER suggest a double angle with equal legs (2L100x100x10 mm) in both box profile and tee array as an alternative section to pipe fore-poling system while neither L80x80x8 mm nor 2L80x80x8 mm can sustain the axial and shear stresses exerted on pipe fore-poling system.
引用
收藏
页码:1125 / 1142
页数:18
相关论文
共 22 条
[1]   The role of umbrella arch and face bolt as deformation preventing support system in preventing building damages [J].
Aksoy, C. O. ;
Onargan, T. .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2010, 25 (05) :553-559
[2]  
[Anonymous], TECHN MAN DES CONSTR
[3]  
Barisone G, 1982, P 4 C INT ASS ENG GE, V4, P15
[4]  
Carrieri G, 2002, 4 INT WORKSH MICR VE
[5]  
Carrieri G, 1991, P C SOIL ROCK IMPR U, V1, P99
[6]   Numerical modeling of an umbrella arch as a pre-support system in difficult geological conditions: a case study [J].
Elyasi, Ayub ;
Bagherzadeh, Parisa ;
Javadi, Mohammad ;
Moradi, Taher ;
Moharrami, Javad ;
Parnian, Saeid ;
Amrac, Mohsen .
BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2016, 75 (01) :211-221
[7]  
Fethi K, 2015, JORDAN J CIV ENG, V9, P139
[8]  
Gangale G, 1992, TOW NEW WORLD TUNNEL, V2, P873
[9]  
Haruyama K., 2001, INT S MOD TUNN SCI T
[10]  
Hoek E., 2004, Numerical modeling for shallow tunneling