Optimizing planning of build-operate-transfer projects to maximize investor profit

被引:9
作者
Abdallah, Moatassem [1 ]
Alshahri, Abdullah [1 ]
机构
[1] Univ Colorado Denver, Civil Engn, Denver, CO 80222 USA
关键词
optimizing construction schedule; repetitive building operate transfer projects; maximizing investor's profit; TRADE-OFF ANALYSIS; INFRASTRUCTURE PROJECTS; CONSTRUCTION PROJECTS; REPETITIVE PROJECTS; COST OPTIMIZATION; TIME; RISKS; MODEL; STRATEGIES; SAFETY;
D O I
10.1139/cjce-2017-0327
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
During planning of repetitive build-operate-transfer (BOT) construction projects, investors and (or) investor-representatives are always faced with a challenging task to identify an optimal project plan that maximizes the investor's profit within a specified concession period. Minimizing project duration in BOT projects often results in additional costs, however, it increases the project operation period and accordingly increases the investor's profit. Optimal plan of constructing repetitive BOT projects requires identifying construction methods and the associated start and finish time of each construction activity according to the availability of resources and contractors. Traditional scheduling methods such as critical path method (CPM) networks do not provide efficient planning of repetitive construction projects as they (1) do not maintain crew work continuity as well as resources availability, and (2) often result in large and repetitive number of activities to model repetitive construction projects. This paper presents the development of an optimization model using linear scheduling method that identifies the near-optimal plan for constructing repetitive BOT projects to maximize the investor's profit. The development of this optimization model includes three steps: formulation phase that formulates the model decision variables, objective function, and constraints; implementation phase that executes the model computations using genetic algorithms and identifies the model inputs and outputs; and evaluation phase that verifies the model performance and document its value. A case study of a construction project is presented to illustrate the new capabilities of the model. The results of the model showed 21% profit increase as compared to the existing schedule adopted by the investor.
引用
收藏
页码:26 / 37
页数:12
相关论文
共 70 条
[1]   Time-cost trade-off problem in construction project management, based on fuzzy logic [J].
Abbasnia, R. ;
Afshar, A. ;
Eshtehardian, E. .
Journal of Applied Sciences, 2008, 8 (22) :4159-4165
[2]   Time-Cost Optimization Model Considering Float-Consumption Impact [J].
Al Haj, Rana A. ;
El-Sayegh, Sameh M. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (05)
[3]   Build-operate-transfer in infrastructure projects in the United States [J].
Algarni, Ayed Muhammad ;
Arditi, David ;
Polat, Gul .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2007, 133 (10) :728-735
[4]  
Amin U., 2012, P 3 INT C CONSTR DEV
[5]   LOB and CPM Integrated Method for Scheduling Repetitive Projects [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :44-50
[6]  
[Anonymous], 1989, GENETIC ALGORITHMS S
[7]   Problems facing parties involved in build, operate, and transport projects in Egypt [J].
Askar, MM ;
Gab-Allah, AA .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2002, 18 (04) :173-178
[8]   Time-cost optimization of construction projects with generalized activity constraints [J].
Chassiakos, AP ;
Sakellaropoulos, SP .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (10) :1115-1124
[9]   Time and Cost-Optimized Decision Support Model for Fast-Track Projects [J].
Cho, Kyuman ;
Hastak, Makarand .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :90-101
[10]   New Aspects in Time-Cost Tradeoff Analysis [J].
El-Kholy, A. M. .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (04)