Performance prediction of hard rock Tunnel Boring Machines (TBMs) in difficult ground

被引:173
作者
Rostami, Jamal [1 ]
机构
[1] Penn State Univ, Dept Energy & Mineral Engn, State Coll, PA USA
关键词
Performance prediction; Rate of penetration (ROP); Advance rate (AR); Utilization (U); Tunnel Boring Machine (TBM); Rock tunnelling;
D O I
10.1016/j.tust.2016.01.009
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Performance prediction of TBMs is an essential part of project scheduling and cost estimation. This process involves a good understanding of the complexities in the site geology, machine specification, and site management. Various approaches have been used over the years to estimate TBM performance in a given ground condition, many of them were successful and within an acceptable range, while some missing the actual machine performance by a notable margin. Experience shows that the best approach for TBM performance prediction is to use various models to examine the range of estimated machine penetration and advance rates and choose a rate that best represents the working conditions that is closest to the setting of the model used for the estimation. This allows the engineers to avoid surprises and to identify the parameters that could dominate machine performance in each case. This paper reviews the existing models for performance prediction of TBMs and some of the ongoing research on developing better models for improved accuracy of performance estimate and increasing TBM utilization. (C) 2016 Published by Elsevier Ltd.
引用
收藏
页码:173 / 182
页数:10
相关论文
共 19 条
[1]  
[Anonymous], TUNNELL TECHNOL KOR
[2]  
[Anonymous], 1997, DEV FORCE ESTIMATION
[3]  
[Anonymous], 1991, THESIS
[4]  
Duhme R., 2014, P 8 INT S GEOT ASP U
[5]  
EFNARC, 2005, Specification and Guidelines for the use of specialist products for Mechanised Tunnelling (TBM) in Soft Ground and Hard Rock
[6]  
Einstein HerbertH., 1992, Decision Aids in Tunneling
[7]  
FARROKH E, 2012, THESIS
[8]  
Gong Q.M., 2006, THESIS
[9]   Developing new equations for TBM performance prediction in carbonate-argillaceous rocks: a case history of Nowsood water conveyance tunnel [J].
Hassanpour, J. ;
Rostami, J. ;
Khamehchiyan, M. ;
Bruland, A. .
GEOMECHANICS AND GEOENGINEERING-AN INTERNATIONAL JOURNAL, 2009, 4 (04) :287-297
[10]  
ITA AITES, 2000, REC GUID TUNN BOR MA