Performance analysis of the Chena binary geothermal power plant

被引:63
|
作者
Aneke, Mathew [1 ]
Agnew, Brian [1 ]
Underwood, Chris [1 ]
机构
[1] Northumbria Univ, Sch Built & Nat Environm, Newcastle Upon Tyne NE1 8ST, Tyne & Wear, England
关键词
Organic Rankine Cycle (ORC); IPSEpro; Geothermal; Power generation;
D O I
10.1016/j.applthermaleng.2011.02.028
中图分类号
O414.1 [热力学];
学科分类号
摘要
In this paper, the IPSEpro model of the Chena Geothermal ORC Power Plant had been developed and validated using the real data. The validated model was used to investigate the effect of variation in the geothermal source temperature on plant performance. The analysis showed that the variation of the geothermal source temperature affects the plant behaviour. Increase in the geothermal source temperature above the design point increases the working fluid flowrate, decreases the working fluid degree of superheat at the inlet of the turbine (evaporator exit), increases the plant net power output and reduces the efficiency while decrease in the geothermal source temperature lower than the design point increases the degree of superheat up to a certain maximum beyond which it starts to reduce. It also causes a decrease in the net power output and an increase in the plant efficiency. (C) 2011 Elsevier Ltd. All rights reserved.
引用
收藏
页码:1825 / 1832
页数:8
相关论文
共 50 条
  • [41] Sensitivity analysis and dynamic modelling of the reinjection process in a binary cycle geothermal power plant of Larderello area
    Niknam, Pouriya H.
    Talluri, Lorenzo
    Fiaschi, Daniele
    Manfrida, Giampaolo
    ENERGY, 2021, 214 (214)
  • [42] Performance optimization and improvement of a flash-binary geothermal power plant using zeotropic mixtures with PSO algorithm
    Kolahi, Mohammad-Reza
    Nemati, Arash
    Yari, Mortaza
    GEOTHERMICS, 2018, 74 : 45 - 56
  • [43] HYBRID SOLAR-GEOTHERMAL POWER GENERATION TO INCREASE THE ENERGY PRODUCTION FROM A BINARY GEOTHERMAL PLANT
    Manente, Giovanni
    Field, Randall
    DiPippo, Ronald
    Tester, Jefferson W.
    Paci, Marco
    Rossi, Nicola
    PROCEEDINGS OF THE ASME INTERNATIONAL MECHANICAL ENGINEERING CONGRESS AND EXPOSITION, 2011, VOL 4, PTS A AND B, 2012, : 109 - 119
  • [44] BINARY POWER PLANT ANALYSIS.
    Karlson, Thorbjorn
    Geothermal energy magazine, 1985, 13 (03): : 13 - 15
  • [45] Thermoeconomic cost evaluation of hydrogen production driven by binary geothermal power plant
    Yilmaz, Ceyhun
    Kanoglu, Mehmet
    Abusoglu, Aysegul
    GEOTHERMICS, 2015, 57 : 18 - 25
  • [46] Energy, exergy, and economic analysis of a geothermal power plant
    Kazemi H.
    Ehyaei M.A.
    Advances in Geo-Energy Research, 2018, 2 (02): : 190 - 209
  • [47] Energy and Exergy Analysis of Dieng Geothermal Power Plant
    Qurrahman, Alfian Hardi
    Wilopo, Wahyu
    Susanto, Sigit Ponco
    Petrus, Himawan Tri Bayu Murti
    INTERNATIONAL JOURNAL OF TECHNOLOGY, 2021, 12 (01) : 175 - 185
  • [48] Retrofitting a geothermal power plant to optimize performance:: A case study
    Kanoglu, M
    Çengel, YA
    JOURNAL OF ENERGY RESOURCES TECHNOLOGY-TRANSACTIONS OF THE ASME, 1999, 121 (04): : 295 - 301
  • [49] Thermodynamic re-assessment of a geothermal binary power plant operated in a moderate-temperature geothermal field
    Ozcan, Zeynep
    Akkurt, Gulden Gokcen
    INTERNATIONAL JOURNAL OF EXERGY, 2023, 40 (02) : 162 - 181
  • [50] The 125 MW Upper Mahiao geothermal power plant - Largest geothermal steam/binary combined cycle plant starts-up
    Forte, N
    GEOTHERMAL DEVELOPMENT IN THE PACIFIC RIM, 1996, 20 : 743 - 747