Exact project reliability for a multi-state project network subject to time and budget constraints

被引:23
作者
Huang, Ding-Hsiang [1 ]
Huang, Cheng-Fu [2 ]
Lin, Yi-Kuei [1 ]
机构
[1] Natl Chiao Tung Univ, Dept Ind Engn & Management, Hsinchu 300, Taiwan
[2] Feng Chia Univ, Dept Business Adm, Taichung 407, Taiwan
关键词
Exact project reliability; Multi-state project network (MPN); Lower boundary points; Upper boundary points; Decomposition; Subsets; MANAGEMENT;
D O I
10.1016/j.ress.2019.106744
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In a project, the duration of every activity is uncertain because of weather, availability of machines, human resources, and unexpected situations, and the cost is influenced by the duration. For modeling the uncertain durations, a multi-state project network (MPN) is proposed. To understand the performance of an MPN, project reliability is calculated and defined as the probability that a project can be completed within time and budget constraints. All feasible project state vectors are contained in upper and lower boundary points. The previous literature only calculated an estimated project reliability. To obtain the exact project reliability, a decomposition approach is developed to obtain subsets of feasible project state vectors. Each subset is firstly formed in terms of one upper boundary point and all lower boundary points. Each subset is further simplified to reduce the number of lower boundary points for computational efficiency. An algorithm with the decomposition approach is subsequently proposed to evaluate the exact project reliability. A real project of new manufacturing lines is demonstrated with several combinations of time and budget constraints to show the effectiveness of the proposed algorithm, and project managers can make decisions based on project reliability.
引用
收藏
页数:7
相关论文
共 23 条
[1]   A new approach for project control under uncertainty. Going back to the basics [J].
Acebes, Fernando ;
Pajares, Javier ;
Manuel Galan, Jose ;
Lopez-Paredes, Adolfo .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (03) :423-434
[2]   RELIABILITY EVALUATION OF MULTISTATE SYSTEMS WITH MULTISTATE COMPONENTS [J].
AVEN, T .
IEEE TRANSACTIONS ON RELIABILITY, 1985, 34 (05) :473-479
[3]   Ordering Heuristics for Reliability Evaluation of Multistate Networks [J].
Bai, Guanghan ;
Zuo, Ming J. ;
Tian, Zhigang .
IEEE TRANSACTIONS ON RELIABILITY, 2015, 64 (03) :1015-1023
[4]   Search for all d-MPs for all d levels in multistate two-terminal networks [J].
Bai, Guanghan ;
Zuo, Ming J. ;
Tian, Zhigang .
RELIABILITY ENGINEERING & SYSTEM SAFETY, 2015, 142 :300-309
[5]   Computing project makespan distributions: Markovian PERT networks revisited [J].
Burgelman, Jeroen ;
Vanhoucke, Mario .
COMPUTERS & OPERATIONS RESEARCH, 2019, 103 :123-133
[6]   Reliability estimation for a stochastic production system with finite buffer storage by a simulation approach [J].
Chang, Ping-Chen .
ANNALS OF OPERATIONS RESEARCH, 2019, 277 (01) :119-133
[7]   BOUNDING THE PROJECT COMPLETION-TIME DISTRIBUTION IN PERT NETWORKS [J].
DODIN, B .
OPERATIONS RESEARCH, 1985, 33 (04) :862-881
[8]  
Hillier FS, 2015, INTRO OPERATIONS RES
[9]   ON MULTISTATE SYSTEM-ANALYSIS [J].
JANAN, X .
IEEE TRANSACTIONS ON RELIABILITY, 1985, 34 (04) :329-337
[10]   Project Reliability Interval for a Stochastic Project Network Subject to Time and Budget Constraints [J].
Lin, Yi-Kuei ;
Huang, Cheng-Fu ;
Yeng, Louis Cheng-Lu ;
Cho, Yun-Ling .
IEEE TRANSACTIONS ON RELIABILITY, 2017, 66 (03) :689-699