Verification of Incremental Launching Construction Safety for the Ilsun Bridge, the World's Longest and Widest Prestressed Concrete Box Girder with Corrugated Steel Web Section

被引:57
作者
Jung, KwangHoe [2 ,3 ]
Kim, KwangSoo [1 ]
Sim, ChungWook [3 ,4 ]
Kim, JangHo Jay [2 ]
机构
[1] Hyundai Engn & Construct Co Ltd, HwaMyung Bridge Construct Project, Busan Si 618141, South Korea
[2] Yonsei Univ, Sch Civil & Environm Engn, Seodaemun Gu 120794, South Korea
[3] Hyundai Engn & Construct Co Ltd, Inst Construct Technol, Yongin 446716, Gyounggi Do, South Korea
[4] Purdue Univ, Sch Civil & Environm Engn, Lafayette, IN USA
关键词
Bridges; box girder; Prestressed concrete; Webs; structural; Shear stress; Optimization; Construction management; Safety; Korea; South;
D O I
10.1061/(ASCE)BE.1943-5592.0000165
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Ilsun Bridge is the world's longest (801 m in total length) and widest (30.9 m in maximum width) prestressed concrete box girder bridge incorporating a corrugated steel web. This bridge has fourteen spans, twelve of which were erected using an incremental launching method, a method that is rarely applied in this type of bridge. To verify the construction safety of the Ilsun Bridge, this investigation focuses on the span-to-depth ratio, buckling shear stress of the corrugated steel webs, optimization of the length of the steel launching nose, detailed construction stage analysis, and the stress level endured by the corrugated steel webs during the launching process. The span-to-depth ratio of the Ilsun Bridge was found to be well-designed, using a conservative corrugated steel web design. Further, our investigation revealed that the conventional nose-deck interaction equation was not suitable for corrugated steel web bridges. As a result, a detailed construction stage analysis and measurements of this bridge was performed to examine stress levels and ensure safety during the erection process. The results revealed that there are essential design issues that should be considered when designing prestressed concrete box girder bridges with corrugated steel webs and that, when constructing them, the incremental launching method should be used. DOI:10.1061/(ASCE)BE.1943-5592.0000165. (C) 2011 American Society of Civil Engineers.
引用
收藏
页码:453 / 460
页数:8
相关论文
共 16 条
[1]  
Abbas H.H., 2002, P STRUCT STAB RES CO, P361
[2]  
AHN TW, 2003, P KOREAN SOC CIVIL E, V17, P709
[3]  
EASLEY JT, 1975, J STRUCT DIV-ASCE, V101, P1403
[4]  
ELMETWALLY AS, 1998, THESIS U CALGARY ALB
[5]   Corrugated webs in plate girders for bridges [J].
Johnson, RP ;
Cafolla, J .
PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-STRUCTURES AND BUILDINGS, 1997, 122 (02) :157-164
[6]  
*JSCE, 2000, DES CONSTR STAND HYB
[7]  
KIM KS, 2005, K KOREA CONCRETE I, V17, P411
[8]  
KIM KS, 2004, COMPUT STRUCT ENG, V17, P29
[9]  
*MLTM, 2005, KOR ROADW DES SPEC