An Adapted Firefly Algorithm for Product Development Project Scheduling with Fuzzy Activity Duration

被引:3
作者
Huang, Minmei [1 ]
Yuan, Jijun [2 ]
Xiao, Jing [3 ]
机构
[1] S China Normal Univ, Sch Publ Adm, Guangzhou 510006, Guangdong, Peoples R China
[2] Guangdong Univ Finance & Econ, Sch Finance, Guangzhou 510320, Guangdong, Peoples R China
[3] S China Normal Univ, Sch Comp Sci, Guangzhou 510631, Guangdong, Peoples R China
基金
中国国家自然科学基金;
关键词
RANKING;
D O I
10.1155/2015/973291
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Efficient scheduling plays an important role in product development project management, especially for the product development project with fuzzy activity times. In this research a trapezoidal fuzzy number is used to represent fuzzy activity duration, and an improved magnitude of the trapezoidal fuzzy number is adopted for fuzzy time comparison. Firstly, a mathematical model for the scheduling problem with minimizing the project completion time for the product development project is established. Then, an adapted fuzzy firefly algorithm is developed to solve the model. The priority value based coding method is used; the fuzzy parallel schedule generation scheme is adopted to generate feasible solutions, and the brightness comparisons are made before updating fireflies' locations in the proposed algorithm. Finally, the performance of the proposed algorithm is presented by computational experiments based on PSPLIB benchmarks. An example of resource allocation of an electronic product development project is also used to illustrate the effectiveness and efficiency of the proposed algorithm.
引用
收藏
页数:11
相关论文
共 23 条
  • [1] A new approach for ranking of trapezoidal fuzzy numbers
    Abbasbandy, S.
    Hajjari, T.
    [J]. COMPUTERS & MATHEMATICS WITH APPLICATIONS, 2009, 57 (03) : 413 - 419
  • [2] [Anonymous], P INT C COMP MAN CAM
  • [3] Ranking fuzzy numbers by distance minimization
    Asady, B.
    Zendehnam, A.
    [J]. APPLIED MATHEMATICAL MODELLING, 2007, 31 (11) : 2589 - 2598
  • [4] A heuristic method for RCPSP with fuzzy activity times
    Bhaskar, Tarun
    Pal, Manabendra N.
    Pal, Asim K.
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 208 (01) : 57 - 66
  • [5] TOWARDS FUZZY DIFFERENTIAL-CALCULUS .3. DIFFERENTIATION
    DUBOIS, D
    PRADE, H
    [J]. FUZZY SETS AND SYSTEMS, 1982, 8 (03) : 225 - 233
  • [6] An approach for ranking of fuzzy numbers
    Ezzati, R.
    Allahviranloo, T.
    Khezerloo, S.
    Khezerloo, M.
    [J]. EXPERT SYSTEMS WITH APPLICATIONS, 2012, 39 (01) : 690 - 695
  • [7] Fuzzy priority heuristics for project scheduling
    Hapke, M
    Slowinski, R
    [J]. FUZZY SETS AND SYSTEMS, 1996, 83 (03) : 291 - 299
  • [8] Fuzzy project scheduling problem and its hybrid intelligent algorithm
    Ke, Hua
    Liu, Baoding
    [J]. APPLIED MATHEMATICAL MODELLING, 2010, 34 (02) : 301 - 308
  • [9] PSPLIB - A project scheduling problem library
    Kolisch, R
    Sprecher, A
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1997, 96 (01) : 205 - 216
  • [10] STOCHASTIC AND FUZZY PERT
    LOOTSMA, FA
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1989, 43 (02) : 174 - 183