Mathematical optimization for earliness/tardiness minimization in a multiple automated guided vehicle manufacturing system via integrated heuristic algorithms

被引:59
作者
Fazlollahtabar, Hamed [1 ]
Saidi-Mehrabad, Mohammad [1 ]
Balakrishnan, Jaydeep [2 ]
机构
[1] Iran Univ Sci & Technol, Fac Ind Engn, Tehran, Iran
[2] Univ Calgary, Haskaynes Sch Management, Fac Operat Management, Calgary, AB T2N 1N4, Canada
关键词
Mathematical programming; Scheduling; Earliness/tardiness; Automated guided vehicle (AGV); DECOMPOSITION; DESIGN; EARLINESS; MACHINES; AGVS;
D O I
10.1016/j.robot.2015.05.002
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In this paper, a scheduling problem for multiple automated guided vehicles (AGVs) in a manufacturing system is proposed and formulated. Considering the due date of AGVs requiring for material handling among shops in a jobshop layout, their earliness and tardiness are significant in satisfying the expected cycle time and from an economic view point. Earliness results in AGVs waiting and tardiness causes temporary part storages in the shop floor. Therefore, we propose a mathematical program to minimize the penalized earliness and tardiness. Since the mathematical program is difficult to solve with a conventional method, an optimization method in two stages, namely searching the solution space and finding optimal solutions are proposed. The performance of the proposed mathematical model is tested in a numerical example and compared with several methods in the current literature. (C) 2015 Elsevier B.V. All rights reserved.
引用
收藏
页码:131 / 138
页数:8
相关论文
共 37 条
[1]  
Baptiste P., 2001, KLUWERS INT SERIES
[2]  
Baptiste P., 1995, 1 INT WORKSH ART INT
[3]   A time window approach to simultaneous scheduling of machines and material handling system in an FMS [J].
Bilge, U ;
Ulusoy, G .
OPERATIONS RESEARCH, 1995, 43 (06) :1058-1070
[4]   VEHICLE SCHEDULING IN 2-CYCLE FLEXIBLE MANUFACTURING SYSTEMS [J].
BLAZEWICZ, J ;
BURKHARD, RE ;
FINKE, G ;
WOEGINGER, GJ .
MATHEMATICAL AND COMPUTER MODELLING, 1994, 20 (02) :19-31
[5]   A REVIEW OF RESEARCH ON AGVS VEHICLE MANAGEMENT [J].
CO, CG ;
TANCHOCO, JMA .
ENGINEERING COSTS AND PRODUCTION ECONOMICS, 1991, 21 (01) :35-42
[6]   Scheduling and routing of automated guided vehicles:: A hybrid approach [J].
Correa, Ayoub Insa ;
Langevin, Andre ;
Rousseau, Louis-Martin .
COMPUTERS & OPERATIONS RESEARCH, 2007, 34 (06) :1688-1707
[7]   Dispatching and conflict-free routing of automated guided vehicles: An exact approach [J].
Desaulniers, G ;
Langevin, A ;
Riopel, D ;
Villeneuve, B .
INTERNATIONAL JOURNAL OF FLEXIBLE MANUFACTURING SYSTEMS, 2003, 15 (04) :309-331
[8]  
Dotoli M, 2004, INT J PROD RES, V42, P1787, DOI [10.1080/00207540410001661364, 10.1080/00207540310001661364]
[9]   Minimization of earliness, tardiness and due date penalties on uniform parallel machines with identical jobs [J].
Drobouchevitch, Inna G. ;
Sidney, Jeffrey B. .
COMPUTERS & OPERATIONS RESEARCH, 2012, 39 (09) :1919-1926
[10]   Integrated production and material handling scheduling using mathematical programming and constraint programming [J].
El Khayat, Ghada ;
Langevin, Andre ;
Riopel, Diane .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 175 (03) :1818-1832