A novel branch-and-bound algorithm for the chance-constrained resource-constrained project scheduling problem

被引:21
作者
Davari, Morteza [1 ]
Demeulemeester, Erik [1 ]
机构
[1] Katholieke Univ Leuven, Dept Decis Sci & Informat Management, Leuven, Belgium
关键词
project scheduling; branch and bound; uncertainty; chance constraints; resource constraints; STOCHASTIC INTEGER PROBLEMS; DISCRETE-DISTRIBUTIONS; OPTIMIZATION;
D O I
10.1080/00207543.2018.1504245
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The resource-constrained project scheduling problem (RCPSP) has been widely studied during the last few decades. In real-world projects, however, not all information is known in advance and uncertainty is an inevitable part of these projects. The chance-constrained resource-constrained project scheduling problem (CC-RCPSP) has been recently introduced to deal with uncertainty in the RCPSP. In this paper, we propose a branch-and-bound (B&B) algorithm and a mixed integer linear programming (MILP) formulation that solve a sample average approximation of the CC-RCPSP. We introduce two different branching schemes and eight different priority rules for the proposed B&B algorithm. The computational results suggest that the proposed B&B procedure clearly outperforms both a proposed MILP formulation and a branch-and-cut algorithm from the literature.
引用
收藏
页码:1265 / 1282
页数:18
相关论文
共 40 条
[1]  
[Anonymous], 2011, TECHNOLOGY INFORM OP
[2]  
[Anonymous], 2001, THESIS TU BERLIN
[3]   Insertion techniques for static and dynamic resource-constrained project scheduling [J].
Artigues, C ;
Michelon, P ;
Reusser, S .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 149 (02) :249-267
[4]  
Artigues C., 2008, Resource-constrained project scheduling: models, algorithms, extensions and applications
[5]   Robust optimization for resource-constrained project scheduling with uncertain activity durations [J].
Artigues, Christian ;
Leus, Roel ;
Nobibon, Fabrice Talla .
FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2013, 25 (1-2) :175-205
[6]   Beam search heuristic to solve stochastic integer problems under probabilistic constraints [J].
Beraldi, P ;
Ruszczynski, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 167 (01) :35-47
[7]   A branch and bound method for stochastic integer problems under probabilistic constraints [J].
Beraldi, P ;
Ruszczynski, A .
OPTIMIZATION METHODS & SOFTWARE, 2002, 17 (03) :359-382
[8]   SCHEDULING SUBJECT TO RESOURCE CONSTRAINTS - CLASSIFICATION AND COMPLEXITY [J].
BLAZEWICZ, J ;
LENSTRA, JK ;
KAN, AHGR .
DISCRETE APPLIED MATHEMATICS, 1983, 5 (01) :11-24
[9]   An adjustable robust optimization model for the resource-constrained project scheduling problem with uncertain activity durations [J].
Bruni, M. E. ;
Pugliese, L. Di Puglia ;
Beraldi, P. ;
Guerriero, F. .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2017, 71 :66-84
[10]   A heuristic approach for resource constrained project scheduling with uncertain activity durations [J].
Bruni, M. E. ;
Beraldi, P. ;
Guerriero, F. ;
Pinto, E. .
COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (09) :1305-1318