Heuristics for the two-machine flowshop scheduling problem to minimise makespan with bounded processing times

被引:27
作者
Allahverdi, Ali [1 ]
Aydilek, Harun [2 ]
机构
[1] Kuwait Univ, Coll Engn & Petr, Dept Ind & Management Syst Engn, Safat, Kuwait
[2] Gulf Univ Sci & Technol, Dept Nat Sci & Math, Hawally 32093, Kuwait
关键词
scheduling; flowshop; makespan; random and bounded processing times; SUPPLY CHAINS; PARALLEL MACHINES; RANDOM BREAKDOWNS; SETUP TIMES; MODEL; ALGORITHM; SHOPS; MANAGEMENT; BUFFERS; SERVICE;
D O I
10.1080/00207540903321657
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The two-machine flowshop scheduling problem of minimising makespan is addressed where jobs have random processing times that are bounded within certain intervals. The probability distributions of job processing times within intervals are not known. The only known information about job processing times is the lower and upper bounds. The decision concerning the solution to the problem, i.e. finding a sequence, has to be made based on these bounds. Different heuristics using the bounds are proposed, and the proposed heuristics are compared based on randomly generated data. Computational analysis has shown that three of the proposed heuristics perform well with an overall average error of less than one percent. Moreover, for symmetric distributions, it is also shown that one of the heuristics, which applies Johnson's algorithm to the average of the lower and upper bounds, performs best with an overall average percentage error of 0.71. The obtained results are also shown to be consistent with recent results reported in the literature.
引用
收藏
页码:6367 / 6385
页数:19
相关论文
共 41 条
[1]  
Allahverdi A., 2003, International Transactions in Operational Research, V10, P65, DOI 10.1111/1475-3995.00393
[2]   Scheduling in stochastic flowshops with independent setup, processing and removal times [J].
Allahverdi, A .
COMPUTERS & OPERATIONS RESEARCH, 1997, 24 (10) :955-960
[3]   A review of scheduling research involving setup considerations [J].
Allahverdi, A ;
Gupta, JND ;
Aldowaisan, T .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1999, 27 (02) :219-239
[4]  
ALLAHVERDI A, 1995, J OPER RES SOC, V46, P896, DOI 10.2307/2583973
[5]   2-MACHINE ORDERED FLOWSHOP SCHEDULING UNDER RANDOM BREAKDOWNS [J].
ALLAHVERDI, A ;
MITTENTHAL, J .
MATHEMATICAL AND COMPUTER MODELLING, 1994, 20 (02) :9-17
[6]   SCHEDULING ON A 2-MACHINE FLOWSHOP SUBJECT TO RANDOM BREAKDOWNS WITH A MAKESPAN OBJECTIVE FUNCTION [J].
ALLAHVERDI, A ;
MITTENTHAL, J .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1995, 81 (02) :376-387
[7]   A survey of scheduling problems with setup times or costs [J].
Allahverdi, Ali ;
Ng, C. T. ;
Cheng, T. C. E. ;
Kovalyov, Mikhail Y. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 187 (03) :985-1032
[8]   The role of human factors in agile supply chains [J].
Barve, Akhilesh ;
Kanda, Arun ;
Shankar, Ravi .
EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2009, 3 (01) :2-20
[9]   Dynamically allocating expediting funds in projects with schedule uncertainty [J].
Bregman, Robert L. .
EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2009, 3 (03) :363-376
[10]   Selecting performance measurement systems: matching a supply chain's requirements [J].
Brun, Alessandro ;
Salama, Kamal Fahmy ;
Gerosa, Marco .
EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2009, 3 (03) :336-362