Using a risk-based approach to project scheduling: A case illustration from semiconductor manufacturing

被引:21
作者
Zafra-Cabeza, Ascension [1 ]
Ridao, Miguel A. [1 ]
Camacho, Eduardo F. [1 ]
机构
[1] Univ Seville, Escuela Super Ingn, Dept Automat & Syst Engn, Seville 41092, Spain
关键词
project management; risk management; control; scheduling; manufacturing;
D O I
10.1016/j.ejor.2007.06.021
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper introduces a risk-based optimization method to schedule projects. The method uses risk mitigation and optimal control techniques to minimize variables such as the project duration or the cost estimate at completion. Mitigation actions reduce the risk impacts that may affect the system. A model predictive control approach is used to determine the set of mitigation actions to be executed and the time in which they are taken. A real-life project in the field of semiconductor manufacturing has been taken as an example to show the benefits of the method in a deterministic case and a Monte Carlo simulation has also been carried out. (C) 2007 Elsevier B.V. All rights reserved.
引用
收藏
页码:708 / 723
页数:16
相关论文
共 31 条
[1]  
[Anonymous], MODEL PREDICTIVE CON
[2]  
[Anonymous], 2004, INT J THEOR APPL FIN, DOI DOI 10.1142/S0219024904002700
[3]   Generation of optimal schedules for metro lines using model predictive control [J].
Assis, WO ;
Milani, BEA .
AUTOMATICA, 2004, 40 (08) :1397-1404
[4]   SOFTWARE RISK MANAGEMENT - PRINCIPLES AND PRACTICES [J].
BOEHM, BW .
IEEE SOFTWARE, 1991, 8 (01) :32-41
[5]  
Boyd S., 2004, CONVEX OPTIMIZATION
[6]   Resource-constrained project scheduling: Notation, classification, models, and methods [J].
Brucker, P ;
Drexl, A ;
Mohring, R ;
Neumann, K ;
Pesch, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :3-41
[7]  
Chapman C., 2000, Project risk management: Processes, techniques and insights
[8]   APPLICATION OF GENERALIZED PREDICTIVE CONTROL TO INDUSTRIAL PROCESSES. [J].
Clarke, David W. .
IEEE Control Systems Magazine, 1988, 8 (02) :49-55
[9]   RISK MANAGEMENT FOR SOFTWARE PROJECTS [J].
FAIRLEY, R .
IEEE SOFTWARE, 1994, 11 (03) :57-67
[10]   Numerical experience with lower bounds for MIQP branch-and-bound [J].
Fletcher, R ;
Leyffer, S .
SIAM JOURNAL ON OPTIMIZATION, 1998, 8 (02) :604-616